This week our guest is Duane Reid-Carlson, President of EDC Associates Ltd., an independent electricity-focused consulting firm based in Calgary, Canada. The firm focuses closely on Alberta power markets. EDC recently published its quarterly report and had some critical words about the government's proposed changes for Alberta’s electricity market - called the Restructured Energy Market (REM) - describing it as a “highly complex, expensive, inefficient experiment.” The same sentiment was reflected by almost all the 36 organizations that participated in the Alberta Electricity System Operator (AESO)’s feedback process in early 2025. Stakeholders were nearly unanimous in their comments that the changes will make Alberta’s electricity markets more expensive and less reliable - the exact attributes the redesign promised to fix. The sharp criticism spans all industry segments - from natural gas generators and renewable energy developers to consumers and transmission companies. Participants also raised the issue of the AESO skipping the regulatory review from the Alberta Utilities Commission (AUC), which provides an independent review by a regulatory body as a safeguard to prevent any unintended negative consequences from the redesign. Peter and Jackie examine the concerns and potential long-term negative implications for Alberta’s electricity grid, generators, and consumers with Duane Reid-Carlson. Content referenced in this podcast: Stakeholder submissions to the AESO on the Restructured Energy Market (REM) design, January 2025 Please review our disclaimer at: https://www.arcenergyinstitute.com/disclaimer/ Check us out on social media: X (Twitter): @arcenergyinst LinkedIn: @ARC Energy Research Institute Subscribe to ARC Energy Ideas Podcast Apple Podcasts Amazon Music Spotify
Audio and video play straight from the show's own hosting. PodSubs stores and serves no media.
Transcript
From the show. Tap a time to play from there.
SPEAKER_03The information and opinions presented in this Arc Energy Ideas podcast are provided for informational purposes only and are subject to the disclaimer link in the show notes.
SPEAKER_00This is the Arc Energy Ideas Podcast with Peter Turzakian and Jackie Forrest, exploring trends that influence the energy business.
SPEAKER_01Welcome to the Ark Energy Ideas Podcast. I'm Jackie Forrest.
SPEAKER_02And I'm Peter Turzakian. Welcome back. So, Jackie, at Zero Week, which was now a couple weeks ago in Houston, the big gathering of energy stakeholders, I'll call it, the International Energy Agency seemed to make some interesting statements amidst, of course, the whole very loud background narrative in the United States about energy dominance, fossil fuels are the future, drill, baby drill, et cetera, et cetera. And the International Energy Agency has really sort of almost fed into that now. Is that?
SPEAKER_01Yeah. Well, so Fatih Barol, the head of the IEA, said there is a need for oil and gas investment full stop. Well, compare that to the 2021 message, where companies should not invest in new oil, coal, or gas projects to meet net zero 2050. So to me, you know, there's some nuances in the words, but that's a big change in message. And you and I have had many debates about these imaginary net zero scenarios and how they're really not great because people are sort of viewing an imaginary future and not preparing for a realistic one. Right.
SPEAKER_01And so I'm hoping that the IEA is going to come out with a realistic outlook. So we'll look for their world energy outlook uh this fall. But it's rumored they might have a slower net zero scenario, or maybe even we'll go back to seeing a scenario that they used to have pre-2020 when they were a bit more reasonable, showing kind of what current policies would get us.
SPEAKER_02When is their next uh big report coming out? That's a month.
SPEAKER_01It's the fall like of uh 2024. Oh, the fall, so well, not until October usually. Right.
SPEAKER_02But they do have a monthly energy report that comes up, but this is the big thing.
SPEAKER_01Yeah, the big one that had those, you know, the net zero scenario. And uh, you know, in 2021 came out with messaging around no more investment in oil and gas, which really did affect, I think, how people viewed you know the oil and gas industry as a sunset industry.
SPEAKER_02Right. Well, there definitely is, I'll call it change of tunes going on everywhere. And uh, including here in Canada, yeah. Another topic that's front of mind is, of course, the federal election, which has just been called. We're gonna be following that, and we'll have no shortage of things to talk about, particularly from an energy perspective. Well, speaking of energy at large, let's talk a little bit about electricity. And let me ask you, the audience, if this morning, when you woke up and flipped that light switch, you wondered where the electricity came from or when you put the coffee pot on.
SPEAKER_02I certainly didn't, I have to confess, although every now and then I do think about these things given that Jackie and I live and breathe energy. But we need to have a conversation about electricity, electricity in particular in Alberta, because behind that light switch, things are getting quite heated. And we have had guests on the podcast that have talked about our Alberta electricity grid. We've talked about the clean electricity regulations, we've talked about the ASO, the Alberta electricity system operator.
SPEAKER_02But there's a review going on, and we've talked about that, Jackie, right, as well on the podcast. So we're delighted today to really get into some of the contentious things going on behind the scenes. And we've got a special guest, Dwayne Reed Carlson. He's president of EDC Associates Limited. I've known Dwayne for a long time, and I know that his consulting firm specializes in electricity. And I don't know, you've been doing this for decades. So you are the voice of experience here. But Jackie, one of Dwayne's reports sort of tweaked your interest, and that's why we're bringing Dwayne aboard.
SPEAKER_01Yeah, that's right. So welcome, Dwayne.
SPEAKER_02Thank you.
SPEAKER_01You know, Dwayne, I'm really happy to have on because I've actually wanted to do this episode since the beginning of the year, but we've had tariffs and everything else going on. But earlier this year, the Alberta electricity system operator, ASO, as you just said, Peter, asked for feedback on this redesign of the Alberta electricity market, which is actually a really big thing. It's not just the market, it's how they do transmission. There's just a whole range of changes being proposed. And I have to say, there were 36 organizations that participated in this now public document, which we will put a link to in the show notes.
SPEAKER_01But it's scathing, it's concerning. And I really want Albertans to know that almost every company that's involved in the power markets, whether you're a generator, a transmission company, a consumer, uh, across the board, a distributor is very angry about where we're at and very concerned about the future of reliability and affordability of electricity in this province. And your firm put out an excellent report. You do that every quarter, and we will put a link to that in the show notes, not the report, but to uh how people can find out about your firm and ask about getting the report.
SPEAKER_01You also had some critical words. You called the Alberta Electricity Redesign highly complex, expensive, and inefficient experiment. So with that, Dwayne, we're just happy to have you on and get more awareness to this issue.
SPEAKER_02Great. Thank you. Well, Dwayne, I mean, let's just project ahead. Are the lights going to go off when the switch goes on?
SPEAKER_03Likely not, but we might have trials and tribulations with respect to that if we get into trouble uh down the road.
SPEAKER_01All right. Well, let's get into the details. But before we do that, I think it's probably just good to give people a bit of background about Alberta power markets. Prices right now, consumers are enjoying fairly low prices. And the whole point of this redesign was to have affordable pricing. And we had very high pricing in the previous years. I think average power price in 2022 was$147 a megawatt hour. It's about a third of that right now. So, you know, we don't seem to have an affordability issue right now. Because can you tell us like why are prices soft? And do we even need this redesign considering that?
SPEAKER_03Well, that's a good question. Just to be a little more accurate, uh, prices averaged$133 a megawatt hour over 21 to 23, so that three-year period, which equates to the highest price that we experienced previously in the market in the year 2000. But that was for a three-year period. Prices uh have fallen to$63 a megawatt hour in 2024 and averaged, as you pointed out,$41 a megawatt hour year to date 2025. So the cause of that, which was well known for over the last four years to anybody watching in particular, was 13,500 megawatts of generation has been added.
SPEAKER_037,500 megawatts of thermal, 6,000 megawatts of renewable, and 5,000 megawatts of that was developed in the last year alone in 2024. And 3,000 megawatts of that was a conversion of coal to natural gas. So all of that has conspired and come along and is now operating, and prices have miraculously fallen, as fully expected by us, our forecasting, our firm, and everybody that subscribes to our reports had insight to that, including the government of Alberta.
SPEAKER_01Right. So there's no affordability issue now. But let's start out then with why are we doing this redesign? It was about a year ago that the Alberta government announced these sweeping changes. In your view, what problem were they trying to solve? And, you know, what's the process?
SPEAKER_03So basically, the government's stated objectives for their market intervention, as it is, were three things high prices or affordability, or market power concerns, or abuses thereof, and reliability. And as you know, there were two broad steps to the process. The first uh was the interim measures that took effect in mid-2024, and the subsequent restructured electricity market uh process that's now underway, which is uh expected to be completed by 2027 when the interim regulations expire.
SPEAKER_01Well, so that that was the stated goals that they wanted to, but this document, uh, which I will put on, and I think I think a lot of Albertans should read at least parts of this. You know, a broad group of stakeholders are consistently saying that this new design has a big risk of increasing electricity costs, reducing new investment in the province, and reducing reliability. Just the things that this whole redesign was expected to solve, it seems to be making them worse. Described by one submitter, a highly experimental, bespoke, and unconventional, untested design.
SPEAKER_01There's other words like it's an exotic product, it could create harm in reliability and investment, it's outrageous, could lead to market failure. These are things that, you know, very credible companies are saying about this redesign. So, and I know there's so many details to get into, and we'll get into kind of the in concerns of different types of participants because I do have different lenses on this. But what went wrong here? Why are we at this point, a year later, with almost everyone in the industry saying that this is almost a disaster?
SPEAKER_03Well, uh, again, another very good question. And there's many reasons to dislike the initial design scope, and everyone has pointed out from their lens their own favorite element to dislike or hate. But I think the most common thread is just the sheer size and complexity of the scope and scale of the endeavor, uh, which is quite unique and as many people have called it, bespoke.
SPEAKER_01Yeah. I think there was one quote that in Texas and California, they tried to do something similar in terms of like such a full wholesale change of everything at once. And it took something like seven to eight years. And what is the time frame that we're trying to get this done in?
SPEAKER_03By 2027 is the uh target.
SPEAKER_01Right. So in two years. And then some of that is actually kind of implementation time, but the actual design is like a year and a half or something, right? Exactly. Like, like really, really, really tight.
SPEAKER_02Really tight. Let's just sort of back up here for a second. This word design, what does that mean? Electricity redesign? Does that mean like we're trying to redesign, first of all, how electricity is traded. We're trying to redesign who can get onto the electricity grid in terms of whether it's natural gas-fired power versus renewables. Maybe just sort of talk to us broadly speaking, help our audience understand what this nebulous word redesign means.
SPEAKER_03So, market redesign is taking the current structure that we have in place, which is an energy-only market design, which is very simple in its nature. It has its various degrees of complexities, like any market does, but very straightforward. Generators uh put their power into the market, it's assembled by the ISO, and the dispatch occurs and prices settled against load. Very simple structure. So now they're looking at uh taking that and putting in more complex systems and procedures with respect to many things, and I won't get into all the details, but just the redesign of how generators interact with the market, how price formation takes place and how revenue is generated.
SPEAKER_03Right.
SPEAKER_02So, I mean, if I could sort of characterize it, uh we all, as I said in my opening comments, turn the lights on in the morning, put the coffee pot on, then there's sort of a surge in demand as everybody wakes up, and then as they come home again, you know, the maybe fire up the electric stove, turn on all the appliances and the television sets, and maybe even plug in your electric vehicle. So the dynamics on the demand side, we sort of understand, and they're growing. And then there's a supply side, which includes like used to be coal, now dominantly natural gas fire generation in this province.
SPEAKER_02Now we've got a lot of renewables coming in. And so the suppliers are coming into the market and selling through the system operator, and the consumers have prices that they pay, mostly which are regulated by some mechanism. And so what you're talking about is changing the whole structure of about how the goods of electrons are supplied in this market and how we as consumers consume them. And that's everything behind the light switch that I talked about this morning.
SPEAKER_02We have no idea what's going on, but the redesign is going to change the way the flows of electricity are going to occur, how the prices are settled, who makes money and who doesn't.
SPEAKER_03Is that it? That's essentially correct. And a lot of the change has been driven, as I said, from cost concerns, but more importantly, reliability and operational considerations that the ISO is having to struggle with maintaining the system operations and the ramp rates of thermal, which aren't that quick, versus the ramp rates of renewable, which in in the scale that we now have are creating problems in terms of how quickly some of the uh renewables can come and go and how hard it is to manage against the thermal generation to backstop that and manage managing the two.
SPEAKER_03So that's kind of the inner workings of the complexities that are causing problems for the ISO.
SPEAKER_02Let's explore that a little bit more. I always like to use a simple analogy of like a farmer's market. I'm a supplier of peaches, and I can see that uh there's too many stalls with peaches, so I'm not gonna build a plant, right? So if we equate peaches to natural gas fire generation, for example, and I can see that there's too much oversupply, I'm not gonna build a plant. Again, I'm trying to get back to this thing of understanding system redesign. It's like reorganizing the farmer's market and where the stalls go.
SPEAKER_02Who's kind of organizing who pays to come in, who can buy, who can come in and sell, and how the prices are settled.
SPEAKER_03Is this how the prices are created and settled? Basically, if you think about what EDC does for a living, we model the electric system and we've done so for about 33 years. And the energy-only system is fairly simple and transparent. And it's taken decades for us and others who do economic and financial analytics for the power sector, for generators, but more importantly, for their debt and equity providers and their lenders. And so those lenders have gotten very comfortable with the energy market design that we have because they can see a straight-line path through our analytics to how price is formated and how generation is derived.
SPEAKER_03And so from that, they've become comfortable. Contracts no longer for capacity are for the full life of an asset, nor for the full capacity at any point in time. So we're seeing merchant tales and on contracts, but that's suggestive of the industry, the lending industry is very comfortable with the market. What we're moving towards is looking more like a black box. We have not yet uh been able to figure out how to model the REM in its current sort of uh design proposal. And so it's become a bit of a black box. So lenders have put down their pens, they can't see the path to price formation and revenue determination as simply as it was before.
SPEAKER_02So this is gonna create a very uh extend this metaphor, the province is coming in and basically saying, okay, we're gonna rearrange the stalls in the market the way prices are set. And by the way, we're gonna turn the lights out so you can't see where the stalls are.
SPEAKER_03Is that like well, one of the fears that I have is that the government has said affordability is its is its objective. And what worries me about that is when price formation is not determined transparently through a fair and openly competitive process as it is today. Right. It opens for the ISO in this particular case that may be asked or being asked to manage prices through reliability concerns. So what is the catalyst? Like, why are we doing this?
SPEAKER_03Well, the government says affordability and market power concerns and reliability. And so I worry that affordability or price, managing price is the primary concern, and it will be done through reliability means. So market power is when one supplier of electrical power has too much control over the market. And the MSA is in the market, that's its mandate is to look out for those kinds of things and look into it. And over the high price period of 2021 to 23, the MSA was silent. There was no accusation that I'm aware of of anybody doing wrongdoings.
SPEAKER_03There was no collusion, there was no price fixing. You know, there were some hints of maybe prices were higher than they should be, but the MSA didn't do or say anything. So market power is a concern, it's always a concern, but it has tools at its disposal to manage those and uh sort of take care of things. And if they thought someone had too much capacity in the market and could use their position to maximize their price, they could change those rules very easily. The concentration is currently 30%. There's only one participant that's anywhere near that. But that number could be managed to sort of mitigate those fears and concerns.
SPEAKER_01MSA, just tell us what that means.
SPEAKER_03Oh, the market surveillance administrative.
SPEAKER_01And you know, you could argue that the market worked because we had high prices and all this capacity came on and now we have low prices. And honestly, the people that come here and risk their capital are hoping there'll be some periods of high prices, but having to risk periods like this where they make very little money. So we're gonna get to what the solutions are. But you know, Peter, we had the head of the KAISO in California. Elliott, yeah. We had the same issue where there was, you know, renewables coming on and lower utilization for the natural gas generators, and they solved it through much more simple means, which is just providing some payments to those base load generators.
SPEAKER_01We've created something very complicated.
SPEAKER_02So, what's the biggest issue?
SPEAKER_01Well, you know, I think one of the most concerning issues that's throughout this document is the Alberta government has decided to not have the Alberta Utilities Commission, which is also called the AUC hearing, to ensure the proposed design is in the public interest and will keep the lights on at an affordable price. There are comments in this feedback form saying this is a regulatory proceeding that is legally required. There are comments that to do a market redesign with the government just doing it via legislation, which is what they're proposing. We're not gonna go through a regulator who's gonna model this, make sure it works, hear everyone's feedback, adjust it for unintended negative consequences.
SPEAKER_01We're not going through that process because we are so concerned about doing this quickly, that we're just gonna put this in effect without that. And it could lead to significant costs for Alberta consumers. Other comments from the document, deeply concerned by bypassing established regulatory review process. Another comment, they're concerned about the bypassing of regulatory oversight on this, and especially considering you're using an ill-defined, expediated process. So, first of all, it's it's in the public interest that the lights come on, especially in a place like Alberta.
SPEAKER_01If the lights don't come on, remember that January two years ago? Like people, remember what happened in Texas? People died. No, I completely agree. Um, and so the fact that we're just slamming this thing at an accelerated speed through the system and ignoring the requirement to have a regulatory proceeding, to have independent experts who are experts at electricity markets opine and model. You talked about the word modeling, Duane. That's another thing that comes up in here. There's been no modeling to the typical process that you would use to show that this will actually deliver on prices that are affordable and that you will get investment in this province.
SPEAKER_01And even though we are doing those steps, we're skipping the most important part at the end of the process. So enough of my ranting, Dwayne. I'm very concerned by this. Am I wrong to be concerned?
SPEAKER_03No, uh, everybody should be very concerned. And I'm not a lawyer, but there's some question whether uh the government can legally skip these steps. Maybe it can by the you know, the action of a pen, I'm not sure. But they they say they want to skip these steps in the essence of time, recognizing that mistakes will be made anyway, and we'll just fix them on the fly. So, with a bespoke design such as it is, there's sure to be lots of unintended consequences with the design and the IT implementation, notwithstanding a significant cost.
SPEAKER_01Right. Yeah, that's another thing, Peter, that came in through these documents. This is very complex and will require a huge investment in IT infrastructure to manage the prices and things the way that they're proposing. That's not even being talked about really.
SPEAKER_02So, for based on what you know, Duane, like what is the rush that Jackie's talking about? Like what's the rush to ramrod this through without any oversight?
SPEAKER_03Well, other markets representatives like Kaiso and Urcott and others have been to town and have all said that don't take on too much, too much complexity at once at any one time, and don't rush it or or don't arbitrarily rush it, sort of work through it. But by not taking too much on your plate, you're not gonna take up too much time. So taking too long actually causes the market to sort of stand down and you know, wait and see, and all of that creates the fears that we're we're now seeing.
SPEAKER_02In terms of investment to build the electrical incremental capacity that we need to support economic growth, population growth, and AI and data centers and what have you.
SPEAKER_01Yeah.
SPEAKER_03Just to go back to uh during the NDP government's period, they looked at redesigning the market to implement a capacity market, which is more of a bolt-on to the energy-only market rather than a full redesign. That process took several years and got to the point of the AUC decision, which had a lot of input from the experts on that particular instance, whereas this one is not expected to. And that caused a four-year hiatus from generation being developed. Not a very few megawatts were put in place for a four-year period as a result of that process. And it's just a natural response by the market to stand back and wait and see how the market design is going to turn out and how price formation again and revenue determination comes out of it.
SPEAKER_03So they need to understand those things in order to make a financial investment decision.
SPEAKER_01But it's kind of damned if you do and damned if you don't, because if you don't do that process, I think investment stays away too. Because based on reading these, all these people's feedback, none of them are investing in this province. And so, like taking longer or making this shorter isn't going to bring a bunch of capital into this province any faster by the looks of it. It makes people feel even less confident about the durability of this new program.
SPEAKER_03No, and the process, as I mentioned before, is far too broad in its scope and scale. And just far too many things can go wrong.
SPEAKER_02So there seems to be a mismatch as well in terms of the amount of new electrical supply that's coming on in terms of including renewables and this notion of congestion plugging into the grid. And, you know, historically it's been, I guess the term was zero congestion. In other words, anybody could build and plug in and it goes through those big high tension wires and ultimately to homes and factories and everything else in the economy. So, can you talk about what's going on with this whole transmission side and congestion that's now starting to occur?
SPEAKER_03Yeah, that's all correct. We've seen some. Since uh about 2020, there's been a substantial increase to about 3,000 hours in 2024 where congestion has occurred. The ISO estimates that the congestion for the top 10 renewable projects is anywhere from 6 to 12% of production. That equates to about 16,000 uh megawatt hours to up to 50,000 megawatt hours. Yeah, flowing through the wires. That's right. So that that equates aggregates to 16,000 to 50,000 megawatt hours.
SPEAKER_03So not an insignificant amount of energy. But more importantly, uh this translates to about seven to ten percent of their revenues. Uh and that's not insignificant either. So what what is the issue? Not enough transmission lines, or does it go beyond that? Uh well, it goes beyond that. Not enough transmission in certain locations where generation has rushed to connect and sort of overconnected, uh, if you will, uh, with the transmission that's available in those areas. So they rush to where the resource is, the wind resources and the solar resources. Like down in Vulcan places.
SPEAKER_03Yes, in southern Alberta, majority. And so there's been a rush on Alberta. When Alberta opened for renewables quite some time ago, the world took notice. Right.
SPEAKER_02So the rush comes from the renewables. We need more transmission lines. However, with the redesign and all the uncertainties that we've talked about, nobody wants to invest because they don't know what the rules are. So this is the kind of situation that's being created, is that we've got mismatches between the electricity generation, the transmission, the loads going up, and there is not a lot of incentive to invest because of the tremendous amount of uncertainty in what this whole black box market is going to look like.
SPEAKER_03Yeah. And low prices and volatility. We're having more zero priced hours than we ever had, and more 999 priced hours than we ever had. So the pricing has become bifurcated. We're either in a zero dollar hour or in a very high priced hour. Yeah. So is that the max 9999? Right now.
SPEAKER_01They're bringing it down potentially, which no one's happy about. You know, I want to talk about this congestion because I think this is another big issue in terms of scaring capital way outs throughout this document. We always had a zero congestion grid. So if you built a generation project in Alberta, you were guaranteed the transmission or the road to the market. And a lot of people came here with that expectation and built projects, and that has been a long-standing rule. Now, whether that was smart economically or not is another question. So they want to change that. And they have this, I forget it's CAM they're calling it, but some sort of congestion management thing where generators are going to pay a fee.
SPEAKER_01And then that fee will be going towards building more transmission, but there's no guarantee that it will result in you getting more transmission or solving your problem or taking that risk away. And this is one that almost throughout all of the feedback of generators of every type, people see this as a huge barrier to investing. Because if you don't know you can get, you know, the road to get your product to market, you're not going to build your product, you know, like you're not going to build that plant. So it's a big problem. And I also think it's a problem because it's going to apply retroactively to people that build projects thinking that that was part of the deal.
SPEAKER_01And I think that's another thing, Dwayne, that's scares capital away from this province when the rules change so significantly.
SPEAKER_03And through all sectors, the wholesale market as well as a transmission, as you've pointed out. Yeah, there's so many balls in the air.
SPEAKER_02So the renewable generators are quite upset because A, they're not getting on to the grid, and B, the revenue goes down, which Jackie already talked about, therefore the returns go down. Talk a little bit more about the whole renewable surge and that whole constituency. What are they saying?
SPEAKER_01Yeah, I'll just add to that, Peter. You know, I'm on the Canria board, so I'm hearing a lot of this uh first hand, but there's a broad set of problems. They call it like death by a thousand cuts, really. But the way that the market redesign is shaping up, it looks like they're gonna get less money for their product, their electrons. It also looks like they're gonna face curtailment a lot. They may have extra costs. They're saying that their renewables are gonna potentially have to pay uh ancillary fees to, you know, account for the fact that they create, you know, maybe more cost to the system. All in all, most of the modeling is showing that some of these renewables, if not most of them, are going to be cash flow negative under the new system.
SPEAKER_01And some are even saying they're gonna just like disconnect from the grid because they, you know, you can't afford to like lose money every day. I don't know, Duane, your thoughts on the renewables. And, you know, if they were to just disconnect from the grid, that's a big problem, I think. There's something like six gigawatts of total capacity, and they are required now.
SPEAKER_03Yeah, you're correct. Financial harm can manifest itself in many ways to these projects, from increasing the cost to curtailed production, which reduces their revenues. And this would negatively affect their existing and future renewable merchant capacity and PPA evaluations or valuations. So for existing contracted assets, these effects would be felt by PPA contract counterparties through lost value in their PPA.
SPEAKER_02So that PPA is a power purchase agreement where a guaranteed price is a contract.
SPEAKER_03Yep, between generator and buyer. So no project gets built without a PPA. As I said earlier, they're they're now, because of the comfort in the market, in our current market design, they've gotten shorter, less for the length of the asset or for the full 100% of the asset, which has made them easier to contract for buyers because buyers don't necessarily want to take full capacity for the full life of the asset. So there's variability there that's been very good to the market. So what could happen based on all of these rules changing in the market is that PPA buyer is going to be financially harmed through losses with respect to the value of that project or that contract.
SPEAKER_03So you could have contracts that would fail in the hands of a purchaser, which would then roll up onto the project. So the project could become insolvent because it no longer has a contract, now it is exposed to merchant prices. And so that insolvency could occur. I don't think these assets will disconnect from the grid, however, because it's it's just going to take a financial write down and some other party will buy it at a lower price that will presumably the more times it's bought and sold, there'll be a price where it's profitable on under somebody's purchase.
SPEAKER_01Even if it's like generating negative cash flow each year?
SPEAKER_03Well, I don't think it would be negative in aggregate uh necessarily. It could be during certain periods, but yeah.
SPEAKER_02So I mean the renewables aren't happy, and neither are the natural gas fire generators, right, Jackie?
SPEAKER_01Yeah. I mean, the natural gas generators, I mean, many of them are concerned about limiting the upside and the fact uh you alluded to it, Duane, that the price is not as transparent. It's being set by the ASO now, and they're also limiting the market, the highest price and some of these market power interventions. But I mean, the whole point of this redesign, I thought, was to incent more natural gas base load to come on. And I do not think by reading this that it's accomplishing that.
SPEAKER_03No, not at all. Because in part of the REM design, you have an element called an administrative scarcity pricing curve, which gets from the potential lower offer cap for generators,$800 a megawatt versus the current 999. And the only way to get to the price cap, the new price cap that's in proposed,$3,500 a megawatt hour, is through this administrative curve that is administered by who? And that's the ISO. And it's only administered in the event of a scarcity, emergency alert on the system that would create it to move up that curve.
SPEAKER_03But if you think high prices are and affordability is the problem, any movement up that curve is obviously going to get front headlines and perhaps maybe a tap on the shoulder from the parties, the powers that be to, hey, let's not go to prices at such that level for very often. So you know it could arbitrarily be managed through reliability concerns by the ISO.
SPEAKER_01Okay. Well, let's talk a little bit about these interconnects. That's another contentious thing that the province is proposing. Now, you know, interconnects are good in some ways in that they should increase our reliability because, you know, if we have more interconnects, then we have more optionality if we are short power. However, there's a lot of concerns that, you know, you come to this province to build a generator, and um, now they could just flood the market with low-cost power and you never get a high price. And by the way, this is on top of the redesign. So this is an example, Duane, of like you're not only changing the market, but now you're adding all these other things on the side, all changing at once.
SPEAKER_01But what are your thoughts on this plan for? I think there's four interconnects.
SPEAKER_03We actually have three interconnects: 1200 megawatts with BC, 300 megawatts with Montana, and 150 megawatts. It's a DC interconnect to Saskatchewan. So these ties are operated or limited by operational concerns to levels lower than their rated capacity. And their commercial utilization is even lower than that. Having said that, the government wants to get the limits on the transfer capability of the various ties to a higher level so that we could implement or utilize the ties to a much higher level, either commercially or through contract.
SPEAKER_03Increase energy, import or export. Import or export. So Alberta is a net importer. Uh it traditionally has been. Out of the last 25 years, it's been a net exporter only three years. Uh last year, 2024 was one. 2025 and potentially 2026 could also be, uh, given where prices are. So the government wants to increase all the transfer capacity limits uh with respect to the three ties to create a greater opportunity for utilization under various circumstances. The downside to this is that we have differences in the regulatory models that are used in adjacent markets, BC and Saskatchewan, for instance, and even the US, you know, particularly where government-owned utilities exist, which leads to an unfair competitive advantage of parties uh that could uh compete against domestic supply, particularly thermals during peaking situations in Alberta.
SPEAKER_01Okay, so the concern you've got to have a way to manage it so that we can still make money. Okay, Dwayne. Well, uh, we're gonna wrap up here pretty soon, but a couple more questions. I think one that's on a lot of people's minds is while we're changing the whole supply side here and maybe making it very fragile and no one investing in it, at the same time, we're talking about bringing more demand to this province with all of this talk of AI data centers. So I looked at the ASOQ, and currently there's about nine gigawatts of potential new load from AI data centers that have applied to be grid connected.
SPEAKER_01And of course, we know that there's also a bunch of other projects that are saying they don't want to be grid connected, but they would come build here in the province as well. Just looking at the grid connected, you know, our average consumption of electricity in this province is about 10 gigawatts. So that's like talking about doubling demand at a time when the supply side seems rather shaky. So, how concerned are you by that? Like, do you think this demand will materialize and is that going to just add to our problems?
SPEAKER_03Yes. If it materialized in the way that it's it's being announced, it would cause significant problems because a data center, from my understanding, can be built for anywhere from 24 to 36 months and bring some significant load with it where generation to cover that size would take uh six to eight years uh to build. But I think just to update your estimate, I looked at the ISO Q uh last week and it's closer to 12,000 megawatts. But that said, the more I learn about data centers, the more I think there's some significant hype here. And it reminds me of the air barrels uh during the uh oil pipeline nominations of the 1980s and 1990s, which you probably remember very well.
SPEAKER_01So still they'll still happen when the end bridge gets line line gets full.
SPEAKER_03So what I've come to learn is that all uh data center developers plan for future scaling to be able to match the project for the demand, which is exponential, by the way. So, but that said, they will deploy in a very modular fashion if they proceed, where a proposed 400 megawatt site will actually build out in four 100 megawatt phases that could be as far as a year or more between each module as they gain customer contracts to fulfill the data centers. Also, some of the hype is towards the next generation data centers of the thousand megawatt size, which the GPUs for that data center are not even existing yet, but they're under development.
SPEAKER_03So data centers expect to get there. So this is some of the So it's not all happening right away when they put these big numbers out. No, and and just to give some context, uh, there's an estimated 40,000 megawatt of data center load worldwide, which is expected to grow somewhere between 90,000 to 130,000 by 2028. So very aggressive expectations from the industry. But by comparison for Alberta, Ireland, which is a significant data center hub in Europe, took 15 years to build its current 2,500 megawatts of data center load. So based on these numbers in Alberta, should we expect to see some?
SPEAKER_03Yes, we will. Will we see 12,000 megawatts or more? If we do, it'll be in some distant future. We'll see it coming and be able to prepare for it. But as you pointed out, the generation, the REM process and what's going on in transmission and other things are the biggest inhibitor to a data center building because it potentially may not have supply.
SPEAKER_01Well, you know, that's interesting because one of the feedbacks in the document of the 38 participants was from a data center developer. Okay, well, to wrap up, I actually one follow-up question, but if you were sitting there and giving advice to the Minister of Affordability and Utilities, Nathan Dudorf and Premier Smith, what would you suggest they do at this point?
SPEAKER_03Well, it's funny you asked this question because I appointed myself minister for the day during a speech I gave to a NIPSA luncheon last spring. And as minister for this podcast, here's what I what I recommended then. First, if price of power was truly the concern, then I would have implemented a consumer rebate at a reasonable strike price for a reasonably defined short period of time. Just like many other rebates that have been put in place by the Alberta government with respect to natural gas, gasoline, and power in the past. We've done that many times. The government is well of where prices were going, and they were expected to decline once all the new capacity that was under construction hit the market.
SPEAKER_03So this was a relatively low, low-cost fix. Second, if market power and its abuse was a concern, then I would have asked the market surveillance administrator, the MSA, to look into that if they had not already seen existence of those issues, and they were silent during the period of high prices. So we know that potentially was not a problem. Thirdly, and lastly, if long-term reliability was a concern, then I would have tasked the ISO, which is its mandate, to work closely with industry to come up with new market products and procedures and rules to eliminate the perceived risks.
SPEAKER_03So prices are down, check mark. Now they should scale things back. This is what I would recommend now after the fact, because they didn't listen to those recommendations when I was minister of the day a year ago. So now they should scale things back to a manageable scope and scale and work with industry to get it right and then utilize off-the-shelf software that exists that other markets have used and implemented to minimize the errors and to maximize the speed to implementation. That's what I would recommend.
SPEAKER_01So small tweaks add back to the drawing board to just go after those issues that are around.
SPEAKER_03They could probably take advantage of some of the design elements they have today, because not everybody hates everything. There's pieces that that could work, could fit into the market. But uh again, don't do bespoke IT design projects that will take much longer and cost uh much more to complete.
SPEAKER_01Yeah, highly experimental as it has been described. Well, I think uh going back to the drawing board, and how about slowing down and doing this at a reasonable pace with all of the checks and balances, like the regulator reviewing it at the end, too. So, one last question before you go, and we really appreciated your time here, Dwayne is are you buying a backup generator for your home right now?
SPEAKER_03Well, Albertans should be very concerned about future electricity supply, reliability, and affordability. But as Hugh so eloquently pointed out at the top of this podcast, I think the current government actions are more likely to cause the very things that they say they're trying to avoid. However, and saying that, I believe the government's intentions were sincere. I want to make that point. I just think we are not on the right path now, as I as I just outlined. So to answer your question, I'm not buying a generator, I'm not installing a Tesla battery or solar panels just yet.
SPEAKER_03But uh, to be honest, uh all residential and commercial customers don't have the correct bidirectional digital meter to benefit from any of those investments. But when we do, I expect much more innovation would occur.
SPEAKER_01Yeah. And actually that was a feedback too. Why aren't we talking about demand side management around things like giving people incentives to use electricity at different times of the day? Because although you know sending emergency messages to our phone worked in that cold January night, there's got to be better ways of doing it.
SPEAKER_03However, uh, that crude method did work. Uh, we did get a demand response that helped those situations. So uh until we have an AI-driven app on our phones and tablets, you know, we'll have to use the crude methods that we that we have.
SPEAKER_02Well, thanks, Dwayne Reed Carlson, for shedding light, if you pardon the pun, on this redesign issue. Thanks for the work you do in highlighting the issue to the public and those practitioners who are in the business. It's uh great to talk to you. So we'll see how it all plays out. But uh in the meantime, again, thanks for coming. Thank you very much for having me.
SPEAKER_01And thanks to our listeners. If you enjoyed this podcast, please write us on the app that you listen to and tell someone else about us.
SPEAKER_00For more ideas and insights, visit Archenergy Institute.com.
This episode is also available as a video on YouTube. US imports of Venezuelan crude oil rose from nearly 100,000 B/d before this year’s US intervention to almost 700,000 B/d in August. This influx into the US Gulf...
This episode is also available as a video on YouTube. This week on the podcast, Peter and Jackie cover the US midterm election results and their potential implications for energy policy and Canada. They discuss why...
This episode is also available as a video on YouTube. British Columbia has seen a major political shift with the election of a majority Conservative government led by Premier-designate Lorne Doerkson after nine years of...
This episode is also available as a video on YouTube. This week on the podcast, Peter and Jackie review the latest election news, including the BC election, which produced a Conservative majority government over the...
In this week's podcast, Peter and Jackie discuss global oil and diesel markets, the government’s role in major infrastructure projects, including the Pacific Link pipeline, and widening Canadian heavy oil discounts....