North American electricity demand is growing fast, driven by the increasing presence of data centers, as well as other load growth. In Alberta alone, the AESO has reported about 12 GW of requests for load grid connections from data centers.
This week, our guest is Josh Schertzer, Chief Executive Officer at Beacon AI Centers, which recently announced plans to develop up to 4.5 GW of AI data centers in Alberta, representing an investment of up to C$10 billion.
Here are some of the questions that Jackie and Peter asked Josh: Should Albertans be concerned about this substantial load growth and the potential for associated higher electricity prices, given that 4.5 GW would account for nearly a 50% increase in current average provincial demand? Can data centers introduce flexibility by curtailing demand during periods of power shortages? Will Beacon AI Centers rely on grid electricity, or will they build their own generation sources? Do the clients of data centers, such as major IT companies, view natural gas as an acceptable energy source, considering its greenhouse gas emissions? How much cooling water is required, and could freshwater availability become a growth constraint? Lastly, what is the employment impact of the projects, including construction, operations, and spin-off jobs associated with establishing a data center hub?
Content referenced in this podcast:
Globe and Mail, “Carney to brief premiers on plan to fast-track major nation building projects” (May 29, 2025)
The Logic, “Calgary firm eyes $10B AI data centre building blitz” (May 15, 2025)
Duke Nicholas Institute for Energy, Environment & Sustainability, “Rethinking Load Growth: Assessing the potential for integration of large flexible loads in US power systems” (February 2025)
Audio and video play straight from the show's own hosting. PodSubs stores and serves no media.
Transcript
From the show. Tap a time to play from there.
SPEAKER_03The information and opinions presented in this Arc Energy Ideas podcast are provided for informational purposes only and are subject to the disclaimer link in the show notes.
SPEAKER_00This is the Ark Energy Ideas Podcast with Peter Turzakian and Jackie Forrest, exploring trends that influence the energy business.
SPEAKER_01Welcome to the Ark Energy Ideas Podcast. I'm Jackie Forrest.
SPEAKER_02And I'm Peter Turzakian. Welcome back. Well, Jackie, you did it. You got that coveted camping spot.
SPEAKER_01The BC campsite I've been trying to get. And now, Peter, I I don't want to jinx it, but it looks like I'm going to actually see Mount Assiniboyne, which is very exciting. Yeah.
SPEAKER_02Good, good.
SPEAKER_01Of course you've done that.
SPEAKER_02Not for a long time, but I have done that. Okay, great. What's in the news?
SPEAKER_01Today, uh, we're recording a little bit early. It's May 29th, and the Global Mail has just reported that Mark Carney will be visiting Western Canada. There's going to be a Premier's meeting in Saskatchewan on Monday, but I we hear there may be some other meetings.
SPEAKER_02Yeah, I always think there's some meetings here even over the weekend.
SPEAKER_01Yeah. And we had Gordon Campbell on uh last week being a bit skeptical about if this government was going to act. But the reporting in the Global Mail, and I will put an article to it, and by the time this is live, maybe there'll be more, a lot more to say on this, but they're proposing changes to legislation to fast track projects. There'll be a list of nation-building projects, and that these will have a much faster approval process and they will adjust regulations to modify that and to release, you know, relax some of the requirements. And if they are projects of national interest.
SPEAKER_01So more to come on that, but we want to see fast action. They're talking about potentially passing this uh by Canada Day.
SPEAKER_02Yeah. Well, next time we record, we'll know a lot more. We'll know the outcome of that first minister's meeting in Saskatchewan, potentially even some hints on what the list is of infrastructure projects that are prioritized. And I do think there's going to be some legislation that accompanies that. So stay tuned.
SPEAKER_01Yes, stay tuned.
SPEAKER_02All right. Well, we talk a lot about the supply side of energy. We talk a lot about politics lately, unavoidably. We talk about policy that emanates out of the politicians and government. I'd like to come back to one of our favorite subjects, which is on the consumption side of energy, and that's data centers. And still the tremendous momentum behind data centers, the tremendous excitement. I can tell you that I voraciously use AI in my day-to-day productivity. I know you do too, Jackie.
SPEAKER_02So we want to find out more. We want to find out more also because there's some really fantastical numbers and excitement here in the province of Alberta with respect to the build-out of data centers. So who better to invite than a CEO of a data center company? So today we're delighted to have a special guest, Josh Schertzer, who is the CEO at Beacon AI Centers based here in Calgary. Welcome, Josh. Thanks for having me.
SPEAKER_01Okay, Josh. Well, you know, your company wasn't maybe not known to everybody uh a few weeks ago, but there was an article, and we will we'll put a link to it that introduced your company and talked about potentially a$10 billion investment here in Alberta, four and a half gigawatts potentially of electricity demand. So that got a lot of people's attention. And so we're really glad you could join us and tell us a bit more about it. So maybe we could start off with just telling us a bit about yourself and the company.
SPEAKER_03I'll go quickly just into my background first for 60 seconds or so, just to give some of that, and then I'll dive into Beacon and what we're up to. So I am just newly appointed CEO at Beacon. I started in the middle of March, so I'm fairly fresh. I'm coming off of what I like to joke about as a just about a 17 and a half year sprint working at a private equity firm called Blackstone, where I had a number of roles. I was the chief technology officer of enterprise technology. Uh, I was a team of five or six that led early stage investing off the balance sheet on behalf of the firm. I advised both our portfolio companies and our business units on technology-related strategy and investments.
SPEAKER_03And most recently, I was up in New York for the first 13 years of my career at Blackstone. And in 2020, I relocated to Miami to both launch and co-lead that office. That was a really exciting journey for me. Um, it's pretty much the only place I've ever worked other than New York Stock Exchange for a brief period of time. And the story behind me coming to Beacon is Beacon is invested and owned by an investment firm called Nadia Partners that's chaired by someone named Aiden Kehoe, who's a dear dear friend of mine. I sat on the board of Aiden's company years ago that he had successfully sold. And we always knew after he sold that that we would end up working together somehow.
SPEAKER_03And credit to Aiden, he's been trying to figure that out for, you know, trying to pull me over for years. And I can never bring myself to leave in the exciting role I had at Blackstone. But when Aiden approached me again last summer about what they were working on at Beacon AI centers, it really resonated with me just mainly because of a few things. One is my technical background as someone who's built and operated data centers across my career, someone that has built technology, including artificial intelligence technology, for, you know, for quite some time. And really just on the Blackstone side of the house, it's also obviously it's very public that Blackstone is a very large, if not the largest, data center investor in the world.
SPEAKER_03And so I sort of have this like practitioner experience coupled with the exposure I got on the investment side of the house. And so when this opportunity presented itself via Aiden, it excited me quite a bit.
SPEAKER_02Yeah. Well, your pedigree is amazing. And my experience with American PE and American entrepreneurs and CEOs is go big or go home. For sure. So here it's go big and come here and$10 billion. So tell us where you are going to place the data centers here in Alberta.
SPEAKER_03So if you're thinking, so thank you for the support and stuff as it relates to the launch and to the releases a few weeks ago. Uh if I'm being honest, we expected some inbound. Uh it was quite more than we expected in a good way, especially up here in Alberta. If people didn't know who Beacon was before, they certainly do now. And that's, you know, we're very happy about that. We are a data center development company. The problem that we're trying to solve for is essentially the constraint that the, you know, the large technology companies, the hyperscalers face as it relates to the sort of crunch, as we call it, for compute. As they continue to develop and build out artificial intelligence technologies and features, and those things get released.
SPEAKER_03And as they train models, and as these models continue to enhance, there's just a big strain on compute technology, compute power to continue to power that. And so in compute is really just, you know, CPUs and GPUs, mainly GPUs, used to crunch that information. But compute really equals power. You if you don't have significant power, you can't provide that compute. And so it's really a power constraint at the end of the day. And it's no secret that, you know, in North America and more broadly globally, power is obviously very scarce, and grid power in particular is very, very scarce. And so we had done, you know, the credits to the team.
SPEAKER_03The company's founded by a person named Joe Schlovan, a credit to him. We've been here in Alberta since 2023, quietly using data and other sources to really try to find like where the right places are to locate these centers. Alberta is a really exciting place when it comes to building data centers because a number of things. Uh, it's obviously got really great access to natural gas. It does have some excess grid capacity that can be used in the short term. You know, it's got a great workforce, it's very business friendly, et cetera. So all those things really, really matter quite a bit. And so after, you know, again, some really careful research and decision making over the last two years, we made some investments in a number of sites.
SPEAKER_03The six that you read about in regards to that 10 billion that you just alluded to are the ones that we are uh committed to, but we do have a few other sites up here as well that are a bit more opportunistic in nature. And so we're still trying to explore how to leverage those. Three sites in the greater Calgary area and three sites in the greater Edmonton area. Of those six sites, five of the six of them are capable of what we call what's 400 megawatts of power each. And then the sixth one is actually capable of up to call it between 1.4 and 1.8 gigawatts of power. And so what does that mean per site?
SPEAKER_03So for the sites, for the five of the six sites that are capable of 400 megawatts, it's essentially four buildings, 100 megawatts per building. And the sixth one can obviously go to four buildings, but that's a 960-acre parcel, so it can go quite larger to that, you know, assuming that we can provide the power to it.
SPEAKER_02Trevor Burrus, Jr.: Yeah. Well, I mean, I just I always feel like we need to put these numbers into perspective. So to me, one gigawatt is the equivalent of a mid-sized nuclear power plant. Trevor Burrus, Jr.
SPEAKER_03That's correct.
SPEAKER_02And so 400 megawatts is like a very large gas-fired power plant that serves a large fraction of a city.
SPEAKER_03We were having a meeting earlier today, and somebody actually was also trying to put that into context. And essentially, you know, that 4.5 gigawatts, don't quote me exactly on the numbers here, but uh that 4.5 gigawatts is uh basically almost three calories if you talk about the power that the power required to power the entire city. Trevor Burrus, Jr.
SPEAKER_01Well, and the province is uh on average consuming about 10 gigawatts, although our peak is closer over 12. But uh just to help our audience understand what a big load that is. Now, that load has come with some concerns as well. Sure. Because it's not just your project, the ASO, which is our electricity system operator, has 12 gigawatts of data center load in their queue. You can see your six projects, but there's others there as well. And if all this demand were constructed, you know, we're talking about doubling our consumption. And that doesn't even include, by the way, there's other projects that have been announced that aren't connected to the grid, which would add another 10 maybe to that.
SPEAKER_01So, how should Albertans look at this? Or should you know, you say we have some excess capacity now that could be easily consumed? And I know Beacons are aware that we're redesigning our electrical system right now, because you were actually uh contributors to some of the feedback to the government on that. And right now, it's not really the best environment to get people investing in generation. So, how should we look at that? Or should we be concerned by it?
SPEAKER_03Yeah, I would say a few things. Well, one thing I should clarify it can be consumed, but I should say we feel it could be safely consumed. Now, granted, there's obviously concerns around some of that. But first off, everything that ASO and you know the broader regulatory parties are doing here is the right thing to do. They've got obviously a lot of demand that came within a very short period of time, coupled with, as you mentioned, trying to do things to expand and reinforce the grid more broadly for the future. And so we were just with one of the ministers today who was alluding to something very similar. And uh it's a legitimate thing to focus on. And so I think that the steps that the ASO are taking here in terms of ensuring that the reliability of the grid is there, ensuring that the cost for electricity for the broader Albertans doesn't go up as a result of what's happening here with this large demand that's coming in is imperative.
SPEAKER_03And so, you know, our hats are off to them for the hard work that they're doing to do this in such a short period of time. Our view is this the great thing about Alberta is that it is an unregulated market. So to some extent, even though there is work and there's policy and things that need to really be either updated or reinforced, et cetera, the fact of the matter is that the opportunity to expand this grid safely and quickly is pretty remarkable when you compare it to other regions, particularly in the United States, where it's a lot harder to do this. It does come with things that need to be like with that, we need to remain focused on.
SPEAKER_03But that being said, it is the right environment for it, if that makes sense. Our approach is sort of a hybrid one. So we are running a business here, but we're also, you know, one of our biggest values at Beacon is essentially like really to make sure that we are really working with the communities in which we're operating. The broader community in Alberta, essentially, like everyone really is excited for Alberta to become the next sort of hub for artificial intelligence. In order to do that, like to some extent, you you need data centers to do that, right? The approach we're taking at Beacon is in order for it to be an AHI up, that means technology companies have to come here.
SPEAKER_03They have to land here, they have to work here. People would obviously get the opportunities to work at these companies, et cetera. But you ultimately have to land the technology companies here for this to effectively become an artificial intelligence hub. So because we are solving the compute constraint that the hyperscalers, the technology companies are dealing with, we're sort of representing what they're looking for.
SPEAKER_02Yeah, let's unpack this a little bit more because we throw this term data center around as if it's some monolithic building filled with racks of computers with blue flashing LED lights. So is Beacon constructing and running the building like a commercial real estate enterprise? Are you actually running the GPUs, CPUs, and the server racks? Yeah. Or all of the above, or what are you doing?
SPEAKER_03So it is commercial real estate, but I would say it's fairly specialized. And like building a commercial office property is nothing like building a data center. It's way data centers are way more complicated, way more expensive to build. So there's sort of three stages to building data centers. Powered land, which is basically just a large land parcel that's got close proximity to power, water, fiber, and transmission lines and things like that. Then the next phase of that is what's called powered shell, which is essentially everything in the powered land phase, but you're also building the walls. You're also, you know, you're building the cooling, you're building all those other pieces. Then there's what's called built-to-suit or turnkey, where you're actually customizing it fully for a particular customer hyperscaler.
SPEAKER_03And then there's the running of those data centers. Currently, our strategy is to take it to the powered shell level. And the reason that we do that is a couple of things. One is uh there are obviously other data center operators out there that have done this at scale. And so for us, it doesn't really make too much sense to invest in something that someone else is great at, and we prefer to partner with them in that. The second piece of that is a lot of these large-scale technology companies, these hyperscalers, prefer to either run it themselves or use one of their operators. Does that make sense?
SPEAKER_01Um, like the Microsofts or the Amazons, they'd prefer to buy the servers and configure them the way they like.
SPEAKER_03Yeah, they all have they actually all have their own specs. And so so for us, we're trying to create the most optionality we possibly can for them and not like not make it for a particular one. Now, if one of them came to us and said, like, look, like we want three of these sites and like we know exactly what you want to do, like we would absolutely be open to that too.
SPEAKER_02But so are you what I guess what is a beacon selling? Is selling and to whom? Are you selling to Microsoft and to Google? Yeah.
SPEAKER_03So we're we're definitely going to those large-scale technology companies, Microsoft's, Googles, Amazon's, Metas, you know, Oracles of the world, basically coming to market to them with a powered shell. And then basically saying, like, here's a powered shell, you know, you know, how much capacity do you guys need? And like, do you how far do you want to take it? Do you want us to build it all the way, or do you want to take it to the powered shell and go from there?
SPEAKER_02Yeah.
SPEAKER_01Okay. Now you've come to Alberta. That's great that you've kind of scandal of North America and see this as a great uh opportunity. But one question I have, one of the criticisms I've heard is that although our energy price at this moment is quite low, it's been volatile, and then we have fairly high transmission costs relative to some other jurisdictions. So, like, how important is electricity price? Obviously, you settled on Alberta even with that. So just kind of explain that too.
SPEAKER_03Yeah, I say two things. Well, electricity price is clearly important to us. It's also important to all of Burton's or any community that you would host this type of stuff. So today, you know, and this is public data coupled with our own math and analytics, but the current price per kilowatt for electricity here in Alberta is quite similar to many of the popular regions in the United States that host data centers. In some areas, it's cheaper. It's actually slightly cheaper than Texas at the moment, according to our math.
SPEAKER_01Even with the transmission costs and everything in and the distribution. Okay.
SPEAKER_03At the moment at the moment.
SPEAKER_01Right. Because we have really low energy cost portion right now. Yes.
SPEAKER_03At the moment, right? But I think, you know, but uh there's a few things I would say there. One is in order to maintain costs and for like, you know, for operators like us that are going to draw this much power not to create more expensive electricity, both for ourselves and for the broader burdens, there's got to be a way to do that. So our approach, it's really a hybrid approach. So it'd probably be helpful for me to kind of explain how we're thinking about the power and how we plan to come online and phase it in because I think it'll it'll kind of clear things up a little bit. So, as I mentioned before, like we're representing customers and their needs. And anybody that's speaking, any data center developer or operator that's speaking to hyperscalers today, know that all of the hyperscalers, the names I just mentioned, and uh a long list that you know following that, they are all shopping for what they refer to as called in-service dates, when they can take ownership of the data center and put their stuff in it, right?
SPEAKER_03They are shopping for the end of 2027 and beginning of 2028. And so we're trying to help solve for that in the short term. One, so that we can land customers yes because we're a business, but two, to get them into Alberta. For example, if we can't land them in here in Alberta, where they're they're actively excited about, what ends up happening is again, they have to solve this compute challenge for themselves or their product, their sort of evolution of their artificial intelligence solutions will stall because they're gonna hit a brick wall when it comes to compute. So hence they will essentially go shop in other markets. They will land there, they will commit there.
SPEAKER_03And then it's not to say that Alberta will completely miss the boat, but it's certainly like they now that these folks are all committed financially, they probably won't be able to circle back until 2031, 2032. So we're really striving for like how do we land at least some of them here now and then ramp up over time. And so when you think about that as it relates to power and our power strategy, our approach is gonna be draw from the grid. And by the way, most of these technology companies, the names we just mentioned, they require at least a strong percentage of grid power. Like for the folks that are saying they're gonna only self-generate, especially if they're a new company, and this is not just my opinion, this is like industry knowledge.
SPEAKER_03Like it will be very hard to land them because they have these requirements. And that's really because they care about reliability and so on, and to some extent, like sustainability falls into that as well. So we are committed to hybrid both grid power and self-generation. That being said, self-generation, if we start today, it takes quite some time to come online. That's not something that happens in 18 months or two years. That could take four years. I think the earliest we'd probably be able to come online with self-generation is 2029. And so as a result of that, what we've been sort of trying to collaborate with, you know, with with ASO on quite a bit. And to be fair, it's been a great partnership, and they've really been listening, as has Minister Globish, the Premier Danielle Smith.
SPEAKER_03Like everyone is really trying to listen and understand the problems. And is there an incremental approach that can be taken to get Alberta, you know, started? Right. And the incremental approach is to some extent grid power. Now, it doesn't mean we have to draw all the grid power the second you say we get it, but it's just a matter of like the only way to land someone here in 2027 is to give them some grid power. You know, so let's say, for example, we got 800 megawatts to a gig allocated of grid power out of the excess capacity that's there now, right? First off, we wouldn't even start doing construction or development until 2026.
SPEAKER_03So in reality, 2026 aren't really drawing much except for construction stuff. And then, you know, really what it comes down to is when the hyperscaler lands and puts servers and racks in your data center is when that draw really starts to happen. So even if we were given a gig today, it's not really gonna get pulled until the end of 2027. Fast forward, say that happens, we get that. We land a few long-term leases on these hyperscalers via grid power. We know there's not 4.5 gigawatts of excess grid capacity in the queue. And so self-generation is gonna be required, even if the grid is expanding, it's still a significant amount. And then again, to your point before on reliability and making sure the costs remain, you know, effective and doable, that self-generation is gonna be required.
SPEAKER_03So we definitely intend to do self-generation as well. And our thoughts are that we're gonna do self-generation, but that's grid connected sort of self-generation. And so the thought behind that is like we can also be contributors to the grid to some extent.
SPEAKER_02Aaron Powell So you will fund the development of a of self-generation like a natural gas fire power plant. So we had a guest, uh, I don't know when it was, Jackie, uh several months ago about the backlog of gas turbines and things like that. I mean, so you have to order today if you probably want one now by 2030.
SPEAKER_03Aaron Powell Hence why I was saying if you uh everybody's gonna commit to self-generation, but in reality, what that means due to exactly your point around data center supply chain, it's just physically as much as our desire would be to do it tomorrow, that's just not feasible.
SPEAKER_02I'm hearing that some of the data center proposals are also co-locating close to natural gas fields. Yeah. Because then you can draw from the fully integrated supply chain, right, from the gas molecules all the way to the power generator all the way to the data center. And only have the grid as a kind of like a backup. Is that yeah.
SPEAKER_03I mean, to the extent that's possible, that's definitely one of the areas we're exploring. Um the other one is I mean, you do virtual PPAs with some of the other power companies as well.
SPEAKER_04Yeah.
SPEAKER_03Or you do it yourself. And so to be honest with you, like all of those options are on the table. And so, like, we're actually, I think you said 12 or 14 gigawatts that's in the queue. Some of that are actually these power companies. So, like in reality, and I respect to all you know, all of our peers and everyone that's working here in Alberta, it's pretty common knowledge that not everything in that queue is legitimate data center building right now. It's a lot of them at the power companies trying to claim some of that power for the, you know, as well. But it's okay because like the expectation's gonna be, and if you speak to some of the folks within the government and within ASO, we know that post-allocation, you know, coming up in a couple of weeks, that some of that is gonna kind of clear, you know, clear itself up, but like, you know, some deals will probably be done.
SPEAKER_03But once people know what they're getting, and that number's probably gonna come down.
SPEAKER_01Right. Maybe some duplication.
SPEAKER_03Yeah, there's that, there's certainly some duplication in there.
SPEAKER_01Now, Alberta, we have renewables, but we're primarily a natural gas grid. And we have the perception that a lot of these IT companies only want clean energy because they've made commitments to reduce their emissions. What has the response been when you talk about uh using a grid that's using a lot of natural gas and has emissions?
SPEAKER_03Yeah, it's it's a couple of things. So you know, I think people have come to the call it understanding that in the short term, natural gas is the only way to get them what they need. And so we we'll be doing some renewables too, but the fact of the matter is renewables cannot power a fraction uh, you know, of this the of the amount of capacity that we're looking to bring online. And so it's gonna have to be, again, a hybrid approach. If it's not renewables, I can do it all. Coal is obviously not an option anymore for a good reason. And then you have natural gas and you have nuclear. Technology companies are also investing directly, like the Microsofts of the world are investing directly in the small modular reactors, uh, nuclear power.
SPEAKER_03But you know, what comes with that is very, very long lead time, still faster than you know, than 20 years ago, but still very long lead times and the cost to do so, and obviously the regulatory hurdles that they're gonna have to jump through to get that built, which again kind of gets you right back to natural gas is really the answer. And so to answer your question more directly, the way that they've been getting comfortable with using natural gas more. First off, I'd say if you look recently, Microsoft, is Microsoft or one of the large technology companies, I don't want to quote the wrong one, but one of them recently within the last three weeks, actually was it was in the news because they actually pulled back on some of their sustainability targets for the the next two or three years simply because they are prioritizing continuing to move forward with artificial intelligence over that.
SPEAKER_03And to some extent it's not possible for them for them to hit those targets. So that's like that's number one. Number two is, and obviously quite important, is natural gas coupled with carbon capture. And so, like, if you're gonna say you're gonna use natural gas to do that, do you have a carbon capture plan as well? And what is that? And can you kind of like show me how that's gonna work and what your emissions are really gonna be? And so it is a lot of work because you gotta really, based on the power that they're gonna draw, because it's It's not like it's per customer too. It's not just like people think about in the context of per land or per piece of land or per plot. But if you have four buildings on a on a particular land parcel and it's different clients, it's actually different targets.
SPEAKER_03Right. So you might have one piece of land and four different sustainability targets. And so we have to work through that complexity.
SPEAKER_01One grid. Well, hey, uh, in the long term, Alberta, I think we can do CCS. We already have proven that. We have the reservoirs, we have the people. It's more about the economics, but uh that can also be the part of the future if that's something the clients demand.
SPEAKER_03Aaron Powell, Jr.: I it is. And to some extent, you also have to think like the way that these leases are pretty not to say flexible, but they're different they're structured differently. And so when you work with the customers, and some of these costs are not just bared onto the data center developer, they're also passed right through to the customers in certain areas based on the targets they want to hit.
SPEAKER_01I gotta think if you're willing to back a nuclear plant and pay that much for power, then you might be willing to pay for uh natural gas with CCS too, right?
SPEAKER_03Trevor Burrus, it's it's that coupled with I think I think the technology companies, the customers have also, to some extent, there's and there's a limit here, but to some extent, have also acknowledged that they can't put all of that cost and burden on the data center developers. So they won't they won't be anybody building data centers anymore. Trevor Burrus, Jr.
SPEAKER_02Yeah. Can you talk about reliability? And I guess they call it 5.9s, 99.999% uptime because uh certainly nobody wants to be interrupted during the making of a cat video. So um can you tell us about that?
SPEAKER_03Yeah, sure. You know, I I think it depends on the type we call them AI factories. It's an industry term that's been used over the last few months. Essentially, it's data centers that are purpose-built for artificial intelligence. But within that, you sort of you still have different categories. So you have AI model training. So think of ChatGBT and ChatGPT constantly training and becoming, you know, more intelligent and providing more intelligent answers. And then you have things like inference and and things that are like where it's doing true reasoning and reference. So there's there's two things there. One is the compute requirements are are quite different.
SPEAKER_03Once you start to get into inference, the compute requirements are like nothing the world has ever seen. Training was that like over the last two years, but like that was just the beginning. And a simple example of that is you know, one chat GPT query is basically 10 times more in terms of the draw on the compute side and the power side as a result than a Google search is.
SPEAKER_02Yeah.
SPEAKER_03But we don't pay any more than a Google search. So Well, the technology companies do, though. Like that's a good drawing work.
SPEAKER_02But it is but is uh I I find that we've had this discussion on podcasts before is that okay, then you go to the making of, say, an AI query to write a paragraph and then then it's a short video and then it's a long video. I mean, the power consumption of these things is just astronomical. Aaron Ross Powell You only still pay a flat, relatively meager monthly fee. Trevor Burrus, Jr.
SPEAKER_01And I mean a lot of them are totally free for individuals, anyway.
SPEAKER_02For them.
SPEAKER_01Oh, sorry. I thought you meant for the.
SPEAKER_03Yeah, yeah.
SPEAKER_02I mean, yes. Like my thesis is at some point we're gonna have to pay per use, aren't we?
SPEAKER_03So a couple of things. Like so one is technology features in general, not so much in AI, AI for sure, but in general, when they come out, they tend to be free and then they figure out how to monetize after the fact. You see that happening with OpenAI, changing their corporate structure to be able to monetize that more. So for sure, like they give them out for free because that's the best way you get them hooked. Once you get them hooked, and then down the road, they'll essentially they'll put some version of the phone.
SPEAKER_03Yeah, I'm I mean, I I think to some extent people are gonna like it's like the same thing as like, you know, how many subscriptions do you feel like paying for? Yeah. You know, when it comes to video streaming or something else. I think people are gonna have to be really smart about that. Uh but back to your question. Let me go back to your question on the yeah.
SPEAKER_02The five nines, because yeah, each incremental nine past the decimal point costs exponentially more, I would imagine. Yeah. And so, like, how much do you really need?
SPEAKER_03The first thing on five nines, and to your point on like, you know, customers may be like, oh, you know what? Like, who cares if ChatGPT goes down? I'll just wait. It all depends on the technology and the use case. So, what do I mean by that? Training. So, training models. So, for example, I keep using ChatGBT because that's the most known. ChatGBT is constantly learning. So, when you are giving it whatever prompt, it's giving you an answer. You're then iterating on that answer. You're saying, oh, do this, but do that too, do that too. As you're doing that, like ChatGBT is continuously learning, and that's on a per person, per user, per prompt basis.
SPEAKER_03That training, you can argue, does not require five nines because it'll just produce an answer with what it has at the moment, and it doesn't have to keep learning to give you that answer. The answer might be slightly stale, but it's essentially it could still give you an answer. So training can be paused, right? Because training itself is not user-facing. Does that make sense? Now, when you get into things like inference, let me give you a prime example of where it does matter, right? Think about autonomous vehicles. And like so, if you think about the proximity of those data centers, but also the speed in which they respond to something, right?
SPEAKER_03That's not only running computers in the car, it's talking to artificial intelligence over internet and other things. And so in certain situations, time does matter. Imagine a data center went down and all of a sudden autonomous vehicles like got funky or something. And I'm just giving you one example. Like, I mean, you can think about in the context of airplanes, a whole a number of things that uh autonomously that if they were left, if they went down, it would create quite the scare.
SPEAKER_02So isn't there like network redundancy in all of this? Like if one goes down, the other one's still up. So it just quickly instantly.
SPEAKER_03Yeah, but pipeline doesn't just only apply to power, it applies to uptime as a whole. So you're talking about network connectivity factors into that, power you know, factors into that. All those things factor that. So uh like if the network went down, the power went up, you're down. Right? If the power goes down and the network stays up, you're down. So there's always that balance. And so again, my point being is one last thing is like outside of artificial intelligence, there's other types of data center usage, for example, cloud computing, which was obviously a big thing prior to artificial intelligence. That's essentially every company, every government hosting their stuff on Microsoft and Amazon.
SPEAKER_03Imagine uh like your banking site went down or something like that. Well, you some people might argue that they can wait for it. Others would say like the banking systems must stay up at all times. And so that requires five nines. And so five nines was a thing way before artificial intelligence, is my point. It's always been a thing. It's just becoming more of a thing now. The difference being now is because of the different sort of phases and use cases for artificial intelligence, companies can be smart about where do they really need five nines to your point and where do they not. And not only can they be smart in that regard, they can then say, like, we can do training in a you know, very far remote region and it can turn off and we can lose it for a day and it wouldn't be the end of the world.
SPEAKER_01Following on that, and there was this recent study by Duke University, there's been a lot of talk about it. I will put a link to it in the show notes, rethinking load growth, assessing the potential for integration of large flexible loads. Basically, the takeaway from the paper is that if these data centers could be a bit more flexible, that there's a bunch of spare capacity in the system. You know, the issue is most of the time of the day, we're not using nearly the capacity of the system. Correct. And so they said if just 0.25% of the time in a year that these uh loads could be curtailed, then there would be an extra almost 80 gigawatts of new load in the existing system.
SPEAKER_01So do you think that uh data center owners are going to become more flexible? Because you say the compute is so important and hard to get.
SPEAKER_03I'm happy you asked that because I think there's a there's probably a perception here that's actually really good to address. This doesn't solely fall on the data centers, right? The data centers are hosting that, but remember, what's in that data center, what's drawing that power, data center owners like us, we don't control that or even touch it or even see it for that matter. Right. So it would be the Amazons, the Microsoft, the Googles, the Oracles of the world. It's their servers drawing the power. And to some extent, like there's two ways to solve for this. One is on the data center, and I'll explain that. But the other is uh even NVIDIA, they've announced that they're working to get a lot more intelligent with their GPUs and their chips around like using, you know, when is it going to draw all the power versus when it's actually not being used?
SPEAKER_03Why does it have to draw all that power? Right. So the chip technology in itself is going to get more intelligent, more sophisticated, and say, if I'm not being asked to do anything at this moment, don't draw the power right now. Tune to essentially, like for lack of better term, tune yourself down.
SPEAKER_04Yeah.
SPEAKER_03When that happens, the data center draws less power. Right. So part of this will fall on them too. Now, the other part, now back to the part on the data center providers, this is actually something that's come up quite a bit here within Alberta. The ASO has been very vocal about this for legitimate reasons. What we have proposed and what we've actually committed to with ASO is that in certain situations like particularly in the summertime when everyone's blasting their air conditioner or wherever whenever high like peak demand of electricity is being used, there's things that can be done. We can work with ASO and any other sort of organization that sort of be would be monitoring and operating this to essentially say, like, data centers will always have, in addition to you know, five nines, the reason the other thing that contributes to five nines is not self-generation to produce the power, but backup generation.
SPEAKER_03Right. So if you were to lose, for example, grid power, right? What we the data centers can't go down back to the five nines situation. And so what happens there is we have backup generators, right? And so what we've been sort of working with ASO on is saying, like, look, in the summertime, if we need to pull 400 megawatts off of the grid because of peak usage, if you have a like a sophisticated way of effectively telling us, we can start the backup generators up and run it for 24 hours until the peak goes down. And we'd be happy to do that. That the second thing is once we get to doing our own self-generation, we'll actually be helping contribute back to the grid.
SPEAKER_03Because if we're not using it at that moment, then the grid can happen. We hope that that sh that helps at least not shelve, but at least address some of the concern around peak load usage because it's a legitimate thing. Like not only beacon, any data center operator, the last position they can be in is the reason that you know that they cause the brownout or some type of over, you know, overusage on the grid. You think about it from our perspective, like in addition to being good neighbors, if you will, like we're absolutely incentive to ensure that this stays up because think about the burden and the and the perception that would fall on us if if we created some type of unreliability as a result of what we're doing.
SPEAKER_01Okay. So another concern you sometimes hear around data centers is their use of fresh water. And in fact, there's been moratoriums in some locations, uh, not here obviously in Alberta, but in in other places because of water use. So, how much cooling water is needed? Uh, and you know, we have like a constraint on water in southern Alberta. Do you perceive that to be an issue?
SPEAKER_03Yeah. We're in the design phase ourselves now. So it's a bit hard to say how much water is going to be used. What I will tell you though, water in general, we committed the six sites that we committed to in Alberta, the solution for water for almost each one of those sites will be different based on what the local communities and municipalities allow for. And also you have to factor in things like environmental studies and other things in the surrounding areas before you can really like nail down a water source solution. And not every land parcel is the same. It's not close to the same things, the same proximity to other things like natural habitats, et cetera. So all of that has to really be factored into it.
SPEAKER_03So like there's a combination of that. Obviously, reuse of wastewater is going to be a priority to the extent possible. Liquid cooling, you know, while it's, you know, it's not fully there yet, liquid cooling technology for sure helps with that outside of the water. What I would say, you know, in Alberta, and again, we're still doing is sort of math here with, you know, as with respect to our design. But, you know, one of the great things about Alberta, uh, not if you're from Miami like me, obviously, because it's a bit cold for me, but uh, one of the great things uh about Alberta is that it does, it is a dry and pretty cool climate most times of the, you know, for the the majority of the year, I would say.
SPEAKER_03And so while air can't be used entirely, it's definitely not that cold, especially with GPUs producing this amount of heat. It certainly can help and it can reduce the amount of water required because you can do a hybrid approach here using air and water.
SPEAKER_02Which you can do kind of like a closed loop water system.
SPEAKER_03And you can do that too. But like it costs more, right? But it's quite expensive. But like but my point is to say that is like Alberta has a little bit more of that option. There's certain there's other areas like Texas, you can't like like you're not you're not open in the air, you know, you can't use air like that. You have to cool that air no matter what. Uh we don't have to cool the air, even if we have to cool the air, we don't have to cool it as much as if we would have to cool it in Texas in the summer. Yeah, you know, summer.
SPEAKER_01Yeah, so you'll need it at some times of the year, but for a big part of the year, you you don't have the cooling requirements of a Texan.
SPEAKER_03Yeah, I mean we are building like you know, AI GPU stocked data centers. They will produce heat. My point is that we have a lot more options here when it comes to solving for that cooling issue than we would do in other in other regions in North America.
SPEAKER_02Let's talk about employment because the criticism is like, okay, yeah, you you build these giant warehouses and the racks of flashing lights, and who knows in a few years is AI robots walking around doing all the tasks. And so actually there's a surge of employment for the construction of these things and putting them together. And then after that, it's just this concrete shell, like a like an artificial brain that's operating on its own. So what what what do you say to that?
SPEAKER_03So I say a few things. There's, you know, jobs, we think about it, you know, in sort of different ways and phases, meaning there's you know, construction jobs, I don't think will be automated for by you know via AI for quite some time. So as it relates to the build-out of data centers for the foreseeable future, construction jobs will be there. Yeah. The second piece that, and so like just for context for us, we are estimating give or take 1500 construction jobs per each site that we look to develop for those four buildings per site.
SPEAKER_01Is that over a couple of years?
SPEAKER_03Yeah, that's over probably a two-year period, two to two year period. And then subsequent to that, when the when the buildings are in service or where they go live, you know, we're estimating between two and three hundred. I think we're actually being conserved uh in terms of permanent jobs.
SPEAKER_04Yeah.
SPEAKER_03And, you know, my view, you know, we've we've had third parties actually come in and vet this for us to make sure that that we were thinking about this the right way. A lot of that obviously pertains to the the size of the structure, the buildings, and the things that you're doing in it. But but ultimately two to three hundred jobs. Like if you look, my Microsoft's got a 350 megawatt campus somewhere in the US and they've got over 300 permanent jobs.
SPEAKER_02So maybe a better question based on experiences that you've seen in these sort of Microsoft campuses of already established data centers is what sort of peripheral technology jobs spin out in the immediate geographic orbit of a data center? Do you know what I mean? Like outside of the data. Like tech startups and things like that. Is there is that happening or are those still?
SPEAKER_03So we're exploring that too. With respect to tech jobs, I think two things there. You know, there'll be data center-related engineering jobs in the permanent two to three hundred number I mentioned. Separate from that, you know, will data centers themselves create more tech jobs, not on the data centers themselves, is what I would say. Like you're gonna get the stand, you're gonna get the typical like sort of jobs that you expect, security, you know, HVAC engineers, things like that. However, when you build data centers, like we're building hyperscale AI data centers, what happens, and this is proven, you know, all over the United States, all over Europe, all over Asia, is when you have data centers here, what happens is companies that also are building AI stuff.
SPEAKER_03Think of companies that are doing robotics or self-driving car technologies, things like that, where they need to be in close proximity to the data centers, they follow the data centers.
SPEAKER_04Right.
SPEAKER_03So like the jobs that come outside are not because they're working for the data center, it's because they need to be close to the data center to build their technology. And as a result, they tend to come. So we view Alberta as not just a data center AI hub. We view it as an it's like we view data centers as the I'm gonna say draw, but I don't excuse the pun, but like the draw to make it an AI hub because once this is here, yes, you'll get some technology companies here and they'll be hiring with those technology companies, et cetera. But more broadly, anybody that's gonna be building new artificial intelligence technology that needs to be close to a data center, and that's a significant amount, they would move here or or or start from here as well.
SPEAKER_01Okay. And I have another one for you to add to your list, Josh. I've been thinking about this. If we see all 12 gigawatts, which I I don't think will all happen, but if we did, that would equate to about a BCF per day of natural gas demand if it was all supplied by gas. So think about it, it's like basically half of LNG Canada phase one. So, you know, we've been working very hard to get LNG exports out of this country. Well, you know, the data centers can provide uh new demand for our natural gas, and we don't have to build pipelines to get that. So, you know, and then that provides jobs to the province in terms of drilling wells, royalties, taxes.
SPEAKER_01That's that's you're right. So that's another benefit. That's an excellent point.
SPEAKER_03Excellent point.
SPEAKER_02Well, we're running out of time, but I want to ask you a final question. When's the first shovel going on the ground?
SPEAKER_03Uh no later than the first quarter of 2026, but we are striving strongly to get there by the end of 2025.
SPEAKER_02Wonderful.
SPEAKER_03Um, but you should definitely expect to see our first data centers come online towards the end of 2027, and January 2028 would be the latest.
SPEAKER_02Well, Josh Schertzer, Chief Executive Officer of Beacon AI Centers, thanks so much for coming in. I want to obviously welcome you to Alberta. Thank you. And uh thanks for all you're doing. I mean, I it sort of blows my mind in terms of the details that we went into and all the information. It's been great. I all I can say is I think it's a good time to be an electrician. That's for sure out of all this. And uh I'd say yeah, thank you for coming in.
SPEAKER_03Yeah, thanks for having me. Thanks for the support and thanks to the broader Albertan community for the the love and support they've showed us. We we couldn't be more grateful. And now that we're pivoting into this next phase, it's our turn to deliver and execute and do what we say we were we came here to do. So we intend to do that.
SPEAKER_01Good. And thank you, Josh, and thanks to our audience. If you enjoyed this podcast, please rate us on the app that you listen to and tell someone else about us.
SPEAKER_00For more ideas and insights, visit archenergyinstitute.com.
This episode is also available as a video on YouTube. US imports of Venezuelan crude oil rose from nearly 100,000 B/d before this year’s US intervention to almost 700,000 B/d in August. This influx into the US Gulf...
This episode is also available as a video on YouTube. This week on the podcast, Peter and Jackie cover the US midterm election results and their potential implications for energy policy and Canada. They discuss why...
This episode is also available as a video on YouTube. British Columbia has seen a major political shift with the election of a majority Conservative government led by Premier-designate Lorne Doerkson after nine years of...
This episode is also available as a video on YouTube. This week on the podcast, Peter and Jackie review the latest election news, including the BC election, which produced a Conservative majority government over the...
In this week's podcast, Peter and Jackie discuss global oil and diesel markets, the government’s role in major infrastructure projects, including the Pacific Link pipeline, and widening Canadian heavy oil discounts....