In this episode, Jason continues the IPCS series by explaining why superintendents and project managers must be actively involved during design development. Builders need time to update the production plan, logistics, zone maps, procurement log, risk register, mobilization strategy, and temporary utility plans before construction begins. Without their early involvement, the project is likely to start without a stable team, an achievable plan, or the preparation needed to execute smoothly. What you'll learn in this episode: Why builders should be engaged by the middle of design development. How early planning improves logistics, procurement, mobilization, and system selection. Why underground utilities, temporary services, permits, and site preparation must be addressed early. How builder involvement supports constructability, prefabrication, and an achievable budget and schedule. Why delaying the project team's involvement can cost weeks or months during mobilization and foundations. Are your builders shaping the project before construction begins, or inheriting an incomplete plan when it is already too late? If you like the Elevate Construction podcast, please subscribe for free and you'll never miss an episode. And if you really like the Elevate Construction podcast, I'd appreciate you telling a friend (Maybe even two 😊). Also, here are links to our YouTube Channels: · Jason Schroeder YouTube Channel: https://www.youtube.com/channel/UC4xpRYvrW5Op5Ckxs4vDGDg · LeanTakt YouTube Channel: https://www.youtube.com/c/leanTakt · LeanSuper YouTube Channel: https://www.youtube.com/channel/UCzQDevqQP19L4LePuqma3Fg/featured · LeanSurvey YouTube Channel: https://www.youtube.com/channel/UC-Ztn3okFhyB_3p5nmMKnsw
Audio and video play straight from the show's own hosting. PodSubs stores and serves no media.
Transcript
From the show. Tap a time to play from there.
Hey there, welcome everybody out to podcast number 1655. I'm going to be talking about what happens if you don't have the component in design and pre-construction of plan with the builders. If you're interested in that, please stay with us. This is the Elevate Construction Podcast, delivering remarkable content for workers, leaders, and companies in construction wanting to take their next step. Get ready to step out of your comfort
zone with Jason Schroeder as he encourages you to do better, live a remarkable life, and expect more. Let's go. Welcome everybody. I hope you're doing well and staying safe out there. This component is really interesting. This is the one that I would probably, actually not having a macro level attack plan early on would really freak me out because then you have the wrong targets.
But the other thing is if I don't start to see builders engaging with the project halfway through design development, I'm going to start freaking out. I mean like light myself on fire, run screaming naked into the woods like panicked because we've got to get this one up and running. Now in this phase, typically design phase, designer pre-construction phase, typically you're going to see the superintendent and the project manager. They're going to be obviously engaging in the
design and pre-con efforts, mainly if they haven't been there before, making it their own or if they've already been a part of it, making sure that everything is finalized, reviewed, and up to date. Meaning that you're going to go through and make sure that your production plan is up to date. You're going to go through your logistics and make sure it's up to date. Your zone maps that it's up to date. You'll start designing your trailer. You'll start your risk and opportunity register. You should have already been working on your
procurement log by now. That's a huge one that we start day one, but you're going to really, really, really start managing that thing and grinding it at this phase. You're going to make sure that you're organizing your team and setting up everything to win. Now, one big thing that I have to remember to say is that you need to look at the property and make sure that there's no underground utilities or shoring or any prep that has to be done early on in order to get the building started. Because if you're talking about permanent power, heck,
that may take quite a bit of time, but that quite a bit of time becomes a problem if it's needed to start foundations. So if you have to reroute a duct bank or a column line or something like that, you've got to get that going right away. OK, so those are the things that happen here. Now, the builders are making it their plan. They're really executing well. They're really helping with the selection of the systems, if not earlier, because if we're following how make homers advice, we need to be selecting systems before design development and then handing
the designers a set of build specs. So we got to get in there. A couple of other things. You know, if you're doing self-performed concrete, you need to start planning and doing lift drillings for that. If it's a laboratory or hospital or an airport, you need to get in with your BDC group and start making sure that you're doing your laser scanning and your modeling and get out ahead of that so that you have your prefabricated spools on time. You're going to be looking at survey. You're going to be looking at temp water. You're going to be looking at temp power.
You're going to be looking at temp communications. You're going to be looking at mobilization. What does the city require? Your permitting plan. You get the idea. But if you don't have this, this is a what probably one of the largest indicators that you are going to fail the project because you've got to get those builders in there and start planning. If you don't have them by design, mid -design development, they're not going to win when it comes to executing the project site.
And they're barely going to get temp water, temp power, trailers and get mobilized to start the dirt work. And even if they do, they're not going, they're going to be, sorry, they're going to be so busy that they don't have a proper method to starting foundations or the superstructure in a before phase planning method. So don't start with the builders. You won't have a team. Don't start with the builders at this point. You won't have a plan. Don't start with the builders. You will not get a final design that's
good enough for you. Don't start with the builders. You will not have a planning schedule and a budget that are actually achievable. And you will start the project behind the eight ball running when you should be smooth and calm. A couple of other things. You will fail the project and enter into the statistics that how big things get done. The authors, Ben Fleverg and Dan Gardner have talked about extensively in their studies. So you will start to enter into the crash landing.
You will have a hard time starting. You will lose two to six weeks in your mobilization foundations phase, if not three months right out of the gate. You will not have the right team and you will not have the right leadership and you will not have stability. This is probably one of the worst things that you can do is not have the builders engaged and involved at design development. So I caution you against making this foolhardy
mistake. Okay. There's so many other any, basically any of the things that Ben Fleverg and Dan Gardner talk about in the book, How Big Things Get Done. You will experience if you fail on this component. I hope you've enjoyed this podcast. On we go. Please join us next time in elevating the entire construction experience for workers, leaders, and companies coast to coast. If you're enjoying the show, please feel free
to share with your construction colleagues and help us spread the word by rating, subscribing, and leaving a review on your preferred podcast listening platform. We really appreciate it. We'll catch you next time on the Elevate Construction Podcast.
Avoiding the hardest problem rarely makes it disappear; it usually gives it more time to grow. In this episode, Jason explains why one of the best ways to improve projects, leadership, and even your own peace of mind is...
When estimating durations, people tend to drift toward one of two dangerous extremes: padding the schedule because they have been burned before, or promising unrealistic performance because they believe they can push...
You do not need authority over the entire project to start leading. In this episode, Jason shares a story from his own career to explain why the most effective way to lead from below is not to wait for permission,...
A three-week pull may look like Lean planning, but Jason argues that it can leave teams focused on what is directly in front of them instead of preparing the entire phase properly. In this episode, he explains why...
A great meeting should do more than share updates it should expose what is off track and help the team solve it. In this episode, Jason breaks down the purpose and flow of the Level 10 Meeting from the Entrepreneurial...