In this episode, Jason challenges the idea that overtime, weekend work, added crews, and late foundations are normal parts of construction. He explains how these warning signs point to failures in planning and leadership, not bad luck. By mapping the work, verifying production rates, coordinating with trade partners, and confirming readiness before work begins, teams can eliminate excuses and build foundations on time. What you'll learn in this episode: Why overtime, weekend work, and added crews signal a deeper leadership problem. How poor planning causes foundation and basement delays. Why historical production rates must guide the construction plan. How pull planning and day-by-day spatial planning improve execution. Why trade readiness, qualified foremen, and mock-ups must be confirmed before mobilization. Are you treating project delays as unavoidable, or are you willing to improve the planning that caused them? If you like the Elevate Construction podcast, please subscribe for free and you'll never miss an episode. And if you really like the Elevate Construction podcast, I'd appreciate you telling a friend (Maybe even two 😊). Also, here are links to our YouTube Channels: · Jason Schroeder YouTube Channel: https://www.youtube.com/channel/UC4xpRYvrW5Op5Ckxs4vDGDg · LeanTakt YouTube Channel: https://www.youtube.com/c/leanTakt · LeanSuper YouTube Channel: https://www.youtube.com/channel/UCzQDevqQP19L4LePuqma3Fg/featured · LeanSurvey YouTube Channel: https://www.youtube.com/channel/UC-Ztn3okFhyB_3p5nmMKnsw
Audio and video play straight from the show's own hosting. PodSubs stores and serves no media.
Transcript
From the show. Tap a time to play from there.
Hey there team, welcome everybody out to podcast number 1650. In this podcast, I'm going to talk about a lack of planning and when you have a problem, two things. If you're interested in that, please stay with us. This is the Elevate Construction Podcast, delivering remarkable content for workers, leaders, and companies in construction wanting to take their next step. Get ready to step out of your comfort zone with Jason Schroeder as he encourages you
to do better, live a remarkable life, and expect more. Let's go. Welcome everybody. I hope you're doing well and staying safe out there. I am excited. I'm home from a trip from Florida. I actually called my buddy Lauren Atwell when I was out there. I'm pleased to know that Petty Coach Schmidt is doing freaking awesome things still out there. I'm so proud of them.
I just love that company. Anyway, I headed home. I'm in a way more jamming out. Couldn't be happier. I'm super stoked. So I got a couple things here. One is I've had this on my notes for a while. Signs that you have a problem and I'm not shaming you. They're trying to make mediocre not normal. I'm trying to make it abnormal. Signs you have a problem. If you or your team are working overtime, if you are adding crews to get done, if you have unmanaged materials, if you have
misaligned workers, if you feel like you're pushing on the project site, if you're working weekends. This is the biggest one. If you're working weekends, you definitely have a problem with leadership on site. And if you are tied to the project, these are signs that you have a problem. The myth is, oh, it's just construction. No, it's not. Construction not done well is abnormal. Construction done chaotically is abnormal. Construction running you in the ground is abnormal.
It's a lack of leadership. And so I want to make sure that's clear that you have any of those signs. You have a massive problem. It's like you went to the doctor and you have you did an MRI and they have found a major growth and they're worried that it might be malignant cancer. So let me start off by winning everybody over. Let me say something else. Almost anything that people say in construction that's normal is usually not normal. One thing that I'd like to tackle today is people talk about foundations.
It's just difficult to come out of the ground. Concrete's always tough. Foundations are always tough. Basements are always tough. No, all foundation delays are because of bad planning. Let me say that again. All foundation delays are because of bad planning. All of them. Let me give you an example. Let me tell you a story. When I was working at DPR, there was actually, it's a funny story. I'm gonna be kind of snarky about this. There was a project superintendent, senior superintendent probably, that was in charge of a massive project
downtown. And he was about six weeks late coming out of the basement. And the concrete contractor was basically doing all the work. And when I went there, I just saw an uncoordinated garbage horrific mess. And they said, yeah, it's just, it's always hard getting out of the ground, right? Just chalked it up to bad luck, right? I did a basement and had it all planned out. We got out of that basement right on time because I learned from the bad example of that senior super just being a victim.
I mapped it all out, did a day -by-day analysis, made sure I had contingency plans. We nailed it, got out of the basement on time. That, it's so funny, I started doing business unit trainings for supers. And supers started to say, now I actually want to come do these. This guy freaked out because he wanted to be next in line to like lead the business unit, took them over. They became the most boring, horrible, garbage things ever in the history of existence.
And then he actually got let go after being assigned some responsibilities that I wanted to take over. Then they apologized and was like, Jason, we're sorry. And then he went to work for a concrete contractor. It's so stupid. Like people reward incompetence in this industry. Anyway, so I'm being a little bit snarky there, but his six weeks late was simply a lack of planning. He didn't plan it well. It didn't work. He didn't know what he was doing.
Every late foundation is simply a failure to map out what it actually takes to build the concrete foundations according to the placement rates and the structural drawings, and to actually map out historical production rates for that specific trade and to do a mock-up and to confirm that the trade is ready to go before they come to the site. That is literally how it is.
And there is no other excuse that if you don't finish on time, you did not plan that right. Now, again, am I trying to shame you? No. We've got to get rid of our excuses. We've got to stop whining and being the victim and blaming everything else because we'll never start to do it right. And we have to start to do it right if we want to get it right. A couple of things that you can do. Check with the trade beforehand. Do lift runs for everything. Check historical production rates. Map it out with a pool plan. Then when you're done with that, map it
out day by day spatially. Confirm that everybody's ready to go. Verify that the foremen are qualified. Literally. And, you know, plus 15 other things if you want to. Foundations don't have to be late. I'm tired of hearing this. Anyway, that's the podcast. I hope you've enjoyed it. On we go. Please join us next time in elevating the entire construction experience for workers, leaders and companies coast to coast. If you're enjoying the show, please feel free
to share with your construction colleagues and help us spread the word by rating, subscribing and leaving a review on your preferred podcast listening platform. We really appreciate it. We'll catch you next time on the Elevate Construction podcast.
Avoiding the hardest problem rarely makes it disappear; it usually gives it more time to grow. In this episode, Jason explains why one of the best ways to improve projects, leadership, and even your own peace of mind is...
When estimating durations, people tend to drift toward one of two dangerous extremes: padding the schedule because they have been burned before, or promising unrealistic performance because they believe they can push...
You do not need authority over the entire project to start leading. In this episode, Jason shares a story from his own career to explain why the most effective way to lead from below is not to wait for permission,...
A three-week pull may look like Lean planning, but Jason argues that it can leave teams focused on what is directly in front of them instead of preparing the entire phase properly. In this episode, he explains why...
A great meeting should do more than share updates it should expose what is off track and help the team solve it. In this episode, Jason breaks down the purpose and flow of the Level 10 Meeting from the Entrepreneurial...