In this episode, Jason continues the IPCS series by explaining why construction teams must build the design team and set clear targets early in pre-construction. He covers the importance of defining success, organizing communication, integrating designers and builders, creating a macro-level Takt plan, and working backward from construction milestones. Without this phase, design teams are more likely to miss deadlines, exceed the budget, ignore builder input, and deliver incomplete or unbuildable designs. What you'll learn in this episode: Why design teams need clear communication, meeting, and planning systems. How a macro-level Takt plan connects design milestones to construction needs. Why teams must design what they intend to build instead of simply building what is designed. How setting the project duration early supports a realistic budget. Why skipping target setting leads to late design, budget surprises, and false value engineering. Are you setting clear targets before design begins, or waiting until the project is over budget to make difficult cuts? If you like the Elevate Construction podcast, please subscribe for free and you'll never miss an episode. And if you really like the Elevate Construction podcast, I'd appreciate you telling a friend (Maybe even two 😊). Also, here are links to our YouTube Channels: · Jason Schroeder YouTube Channel: https://www.youtube.com/channel/UC4xpRYvrW5Op5Ckxs4vDGDg · LeanTakt YouTube Channel: https://www.youtube.com/c/leanTakt · LeanSuper YouTube Channel: https://www.youtube.com/channel/UCzQDevqQP19L4LePuqma3Fg/featured · LeanSurvey YouTube Channel: https://www.youtube.com/channel/UC-Ztn3okFhyB_3p5nmMKnsw
Audio and video play straight from the show's own hosting. PodSubs stores and serves no media.
Transcript
From the show. Tap a time to play from there.
Hey there everybody, welcome out to podcast number 1653. In this podcast I'm going to talk about specifically what happens if you don't have the set the targets phase in your pre-construction efforts. If you're interested in that, please stay with us. This is the Elevate Construction podcast, delivering remarkable content for workers, leaders, and companies in construction wanting to take their next step. Get ready to step out of your comfort
zone with Jason Schroeder as he encourages you to do better, live a remarkable life, and expect more. Let's go. Welcome everyone, I hope you're doing well and staying safe out there. Hey, this topic is really interesting. The second major phase, I would say, of pre-construction is where you set the targets and build the design team.
Now, I use different terminology. Usually the industry will say concept design, schematic design, design development, and construction documents, and I'm fine with that. I don't actually have a problem with that. I use that model quite a bit. But I invented this other five-part step, or I guess you would call it naming, so that people would get a better feel for what happens in each phase. The first one is you do the proposal and the interview.
Second one is you build the design team, not the overall team, but the design team, and you set the targets. And I'll explain that in a minute. The third one is you enable the designers. Fourth one, you plan with the builders. And fifth one, you prepare to start strong. So, let me tell you what will happen if you don't have the build the design team and set the targets phase. Let me go ahead and kick this off by saying first and foremost that most design, and I'm not being offensive when I say
this because I love design, I love designers, but most design teams are wildly unproductive, wildly unproductive. The applications that do design have increased their efficiency by 10 and 2, and I will say sometimes 100 times their original speed. We used to do hand drafting, now we can do it so much faster in programs like Revit or Civil 3D. You get my point. But productivity has declined, mainly because of emails
and silos and batching and not being an integrated design team and basically doing everything in the book that is anti-production. So, design is going to be a pretty big problem no matter what. So, even if you do this step two, you might have issues, meaning that even with the most progressive design teams, you ask them to co-locate, it's going to be difficult. You ask them to dedicate a week or two to critical decisions, it's going to be
difficult. You ask them to get away from email, it's going to be difficult. Doing the real production-minded work of design is typically going to be difficult anyway because the design teams don't want to do it. But, you have a great chance if you head in the direction that I'm talking about. So, build the design team means that you actually do what's called a pre-flight kickoff. You actually go through and identify with the stakeholders what success looks like.
What are the conditions of satisfaction? You organize how you communicate. You organize your meetings. You organize your integrated teams. You organize the effort. You organize your scheduling and pull planning, look ahead and weekly work planning system or your Kanban method system for your daily working intervals. You organize your milestones, right? You're getting everything set together for how we work as a team. And the other part of that is that
you set clear goals and targets. The main thing that you need to set is you need to have a macro-level tech plan at the head of this phase because everything works from right to left. This is how we want to build this project. And this is when we will need to have materials. This is our supply chain. This is when we have to have buyout. This is when we're going to go through and bid the final package. And this is when the design milestones at least per phase or per construction work package
have to be done. And you work it back from right to left. See, a lot of people think that we're just going to build what's in the design. No, we need to design what we want to build. Construction is like designing the manufacturing facility and then actually designing the car. Actually, you would do that beforehand and then actually building the car. We have all three steps. Once the manufacturing plant is built in manufacturing, they only have to design the new model
car, manufacture it. In construction, we have to build the manufacturing facility after designing the car and then actually build the car. Or in construction terms, we have to actually design the building, design the actual production system on site, and then actually build the project. So we have construction is much more complex than manufacturing. Okay, let me say that again. And the reason I mention this is because manufacturing people look down their long, arrogant noses at us in construction. What we do is much more complex than
what they do in manufacturing. Okay, so we must start with a macro level attack plan. Now we know the overall total duration for the entire project. And now we can estimate the proper budget and not be surprised later with a chop and lop design effort that we actually falsely call value engineering, right? So we've got to get those things done. And if you don't have this step, you'll
move away from, hey, there's a chance that I'll fail with the design team too. It is going to be a fact that design doesn't hit their milestones, that they don't actually listen to design assist contractors or trade partners, that they don't get the design right, that it's riddled with problems, it's partially unbuildable, and it's definitely not done for the budget. We didn't target a budget in target value delivery.
We just went over a budget and now it's the lop and chop of design called falsely value engineering. Also, if you don't have the macro level attack plan, you will not queue up construction on time. Also, if you don't have the macro level attack plan and the overall total project duration and then estimate a proper budget, then you will design something that you cannot afford, again, entering into the lop and chop. And you'll do two things.
You'll either saddle the project team with an unbuildable project, which is rude and disrespectful, and they'll just attempt to do it anyway, or you'll surprise the owner so damn much before you reach a GMP that they won't ever want to work with you again. So this is definitely a problem. We've got to build that team. We've got to set up our integrated teams. We've got to set up our communication systems. We've got to set up our meeting structure. We've got to set up how we're going
to schedule in designing pre-construction. We've got to start with a macro level tag plan. We've got to work backwards. We've got to know the duration and we've got to start out with a proper budget that sets us up to win so nobody ever gets disrespected down the road. So this is exactly what will happen if you don't implement this part of the system. I hope you've enjoyed this podcast and we go. Please join us next time in elevating the entire construction experience for workers, leaders, and companies
coast to coast. If you're enjoying the show, please feel free to share with your construction colleagues and help us spread the word by rating, subscribing, and leaving a review on your preferred podcast listening platform. We really appreciate it. We'll catch you next time on the Elevate Construction Podcast.
Avoiding the hardest problem rarely makes it disappear; it usually gives it more time to grow. In this episode, Jason explains why one of the best ways to improve projects, leadership, and even your own peace of mind is...
When estimating durations, people tend to drift toward one of two dangerous extremes: padding the schedule because they have been burned before, or promising unrealistic performance because they believe they can push...
You do not need authority over the entire project to start leading. In this episode, Jason shares a story from his own career to explain why the most effective way to lead from below is not to wait for permission,...
A three-week pull may look like Lean planning, but Jason argues that it can leave teams focused on what is directly in front of them instead of preparing the entire phase properly. In this episode, he explains why...
A great meeting should do more than share updates it should expose what is off track and help the team solve it. In this episode, Jason breaks down the purpose and flow of the Level 10 Meeting from the Entrepreneurial...