Update on Ore Peninsula Cruise Dock Float Executive Session: Matters, the immediate knowledge of which would clearly have an adverse effect upon the finances of the public entity, and matters which by law, municipal charter, or ordinance are required to be confidential: Discussion with the Borough Attorney regarding the Ore Peninsula Cruise Dock Float Packet
Audio and video play straight from the show's own hosting. PodSubs stores and serves no media.
Transcript
From the show. Tap a time to play from there.
SPEAKER_05Okay. I called over to the special meeting of the Skagway Assembly for February twenty second, twenty twenty four. Roll call, please.
SPEAKER_04Mayor Bass present. Assemblymember Henry is uh absent. And we we have one person on Zoom, although we cannot hear them. It may be Assemblymember Burnham, but they will be marked absent if we cannot hear them. Um four members present, quorum is established. Okay, thank you. On to item three, proof of notice, please.
SPEAKER_04Proof of notice is uh at the back of the room, printed on the back of your agenda and posted online. All right. Thank you.
SPEAKER_05Move on to item number four. Hear citizens present. All right. Okay. We've got no one signed up to speak, but I'll open the floor. Has anybody changed their mind? Would anybody like to talk at citizens presence? Okay. We will move on then to item five. Update on Or Peninsula cruise dock float. I'll turn this over to uh manager Ryan. Can you please give us an update?
SPEAKER_02So I think you all have the packet that I have here as well. Um we have the picture of the rendering of what the cruise dock is supposed to look like. Um I'll just keep that up there for now and then I'll I'll be bouncing back and forth between the documents you have and my hand drawing back here that is um not as fancy but allows me to draw on it and help explain the the issue. So um in on uh on the 12th, the morning of the 12th, February 12th, I received a call that the uh cruise float um was having some issues and uh the cruise float was being towed up out of Anaquatus.
SPEAKER_02I believe it left on February 2nd. This was constructed by TransPact Marine, pre-purchased by us. Um turned over to PPM for care and maintenance to be towed up here and installed um in August, I believe. I'll have to look back at that date exactly, but they've had it for for quite a while. Um and they they finally uh went under tow February 2nd to come bring it up here and they made it all the way up to Ketchcan without incident, and then um had some weather and some delays, and they sat and circled there for a couple days.
SPEAKER_02Uh, then they took off to go down around Cape Decision, and about 10 o'clock uh in the morning on February 12th, um, I received a call that said the float had broken into two pieces. It turned out that the float didn't break into just two pieces, it broke into three pieces. Um and with that, then uh Boyer Tug, who was towing it, picked up the pieces and started towing them back to Ketchukan. They started wrangling them. Uh at the same time, PPM sent out um Tug, the uh Alaska Commercial Divers, as well, all to help in this assistance.
SPEAKER_02The commercial divers were going in case there was a leak and they needed to weld up any pontoons. Uh they didn't, but they sent them to be cautious. And there was some reports that there was air bubbling out of some of the pontoons. In the end, um, that was probably out of these um tiny little sections that weren't critical to keeping it afloat. Um, with two tugs and the divers following the floats, the three pieces of the float did make it into the boyard in Ketchikan by Wednesday, which so that would have been the 14th.
SPEAKER_02Um, all three pieces were there. Um, I was there as well by Monday uh to be there and inspect, as was PPM, PPM's Marine Engineers, TransPAC, and KPF representatives. KPFF representatives. Um you have some pictures here. Um I'm sorry, I don't know. Do we have packets back there that we can look at or not? Um in essence, uh, the first picture you have is when it hasn't quite separated into three pieces.
SPEAKER_02Um you have another picture here of it being under tow. This picture represents the three pieces. You can actually see you have two pieces kind of in tandem behind the boat, and then you have a third piece off floating back there in the distance. They haven't picked it up yet, obviously, but it's there. They did not run aground or go aground these pieces. Um the next photo shows um that's actually the middle section of the dock, and you can kind of uh see where the failures were at on the end of the um pilings.
SPEAKER_02I don't know why my phone's beeping when I got it turned up. Um both ends of that failure look the same on that middle section. Um, and then you have some more pictures of it just being tied up in section there, which aren't very telling, but that's what they are. I want to go back to this photo. So just keep this photo in mind right here. So this is the one that probably is the most telling. Um my hand drawing of the failure mechanism in my in my summary so you can understand it a little better.
SPEAKER_02This is the 500-foot float according to my drawing, and this are what we call the cross pontoons or the t's is what I like to call them. You have the center section of float, you have the insections of the float, and these cross pontoons. My understanding of what happened with this is it's being towed, it's a 500-foot long float, it's going up, it's working this area of the cross pontoons, and there's welds along each of these T's onto this cross pontoon. Those welds didn't appear to fail, but instead it seemed to work hard enough that it actually ripped the metal out of these cross pontoons.
SPEAKER_02And if you look at this photo, it looks like these are capped. Those were not capped. That's actually ripping the metal out of the cross pontoon. It doesn't seem like the welds failed necessarily. Um, it just ripped those out. So some forces in there cause this to fail. Now we're all in a debate on whether they towed it in too big a weather, or whether the design was a problem, or the welds were a problem. There's eight people right now, or eight groups, all saying this was the problem, or maybe not saying this is the problem yet, but they're all going to, right?
SPEAKER_02Um, so we're trying to get to the end of that, to the bottom of that. We're gonna hire a third-party engineering firm to do that assessment, but that's not what's important right now. What's important is what is the fix. And the fix, Transback showed up. The fix is, and and we're somewhat fortunate in this. This is a bit of a Lincoln log for people younger than me, a Lego dock. Um, and these round circles are big flanges, two and a half thick, flat flanges that push together, and there's by my count, I didn't really count the bolts, but it looks like a hundred bolts that hold these together in four places.
SPEAKER_02Going under the dock, boating around it. This area, the main structures of the dock, the big pontoons, don't appear to be damaged. Where the flange is bolt up, don't appear to be damaged. They actually ripped out of here, so we can unbolt these sections on both ends, build a new cross pontoon, and bolt it back in. That's easy to say. It it has a there's there's a lot to that. Um, but with that in mind, um, TransPac immediately ordered the steel to do that because the critical path is the steel, because it's two and a half inch thick steel, it's coming out of Oregon, you know, it's it's got to be high-quality steel.
SPEAKER_02That's just for the flanges. The the actual cross pontoons and the little T's that go with it are three-quarter inch steel, and this isn't, you know, they they actually take it to a shop, T Bathe, and they roll this into the tubes. You know, this is big stuff. You know, you you can stand inside of these tubes. Um, so they're in the middle of getting the steel for that one. So step one of fixing it is getting that steel ordered, that steel's ordered. It's due the first week of March. Um step two will be getting that to the manufacturers, T Bailey, to build the flanges, roll the pipes, and get this all welded up.
SPEAKER_02Um the uh all of that should be able to happen and have these delivered to either Ketchikan or Skegway for installation. We haven't sorted that out yet by April 20th. Um in the meantime, between now and April 20th, there is work that has to be done. These cross pontoons that are there and destroyed need to be unbolted, taken out, um, cut in sections now because they don't float, so they're they're big um and prepped.
SPEAKER_02In addition, there was some other damage to the decking on top. Um, there's some I-beams that go across this that need to be set back on their I-beam um mounts, uh, but really most of it appears to be in pretty good shape considering that it came into three pieces. There'll be decking missing when we're done with this, and that'll have to be either replaced this season or maybe next season, depending on how close and how tight we get. But that all at the very least, the cross pontoons and the flange has got to be unbolted and removed and ready.
SPEAKER_02So when these pontoons show up, they can be put in. Um, to put the pontoons or the cross pontoons in, we estimate that to be six to twelve days, depending on how many crews of divers you run. And we'd see that being done May 2nd, um, if that's in Ketchukan. The advantage of Ketchukan is um there are just it's easier to get there, obviously, in the wintertime than us. And there are more resources and more divers there. Uh you know, there's a dive, a commercial diving organization there who has availability, they've been set aside and notified that we need them.
SPEAKER_02Um the disadvantage is PPM is in Skagway and they have their cranes and their big lifting items here. Uh, but Transback has also arranged for a crane bars to be in KetchCan if we decide to go with Ketchcan. Um and I haven't mentioned that, but these cross pontoons are 54 tons, so they're not little. Um, and while you know there's plenty of cranes big enough to do that, it's the reach that gets you in trouble. So you know, I think we all know you can't have a crane way out and lift as much as you can up close.
SPEAKER_02Um get the cross pontoons in by May 2nd. If it's in catchy can, five days or so to get it here. That's May 8th, and then five days to get it installed. Sounds simple. Um, that's the plan right now. Um there are things that are going to impact this. Um the transfer span at a bridge that goes off of the cruise ship dock down to the to the float is uh big, it's heavy, and we originally didn't have a um a head frame there to support it.
SPEAKER_02We're gonna have to add that headframe in there to pick to hold it while it's sitting there and being waiting for this to come in before this dock would have been here on the 14th, and that could have sat right on there. They could have lifted it on with the crane and put it right on the on the dock. Without that, we want to get that head frame here installed so that it can accept that transfer span, which is supposed to be coming up here March 12th. It's a big dock. Um, I think that is the general plan of and timeline of where we're at right now.
SPEAKER_02The debate, of course, and I mean it's every conversation and meeting I had while I was in KetchCan, there's always the who's responsible, who's responsible. Um, my comment to them has always been I know who's not responsible. It's not us. However, we will be forced to most likely fund this up front and fight that out afterwards. We're already getting letters, we're sending letters to all of the organizations involved to put them on notice they can't destroy any records, and that you know, or lose anything, keep all correspondence, and that you know, we've sent letters to PPM and TransPact saying, you know, this is your responsibility, you need to fix it, track your time and materials, and we will sort out the you know, per contract, we'll sort out what you're responsible for and what you're not.
SPEAKER_02Um but it's you know it won't be clear um for a while. Um and right now they're all moving. We'll have to keep them moving and keep them inspired to be moving. And they're all trying to get this done, um, but always money comes down to be an issue. If you want, um, I don't know if anybody wants a you know to go through this is the line drawing of what you what is wrong. Um, it's it's the engineer's version of my crayon drawing, essentially.
SPEAKER_02Um if you look at this, you'll see a red box, and you're all looking at the same um sheet here, I hope. The line drawing sheet, you'll see a red box around it says damaged cross pontoon. That's the T. Those are what came apart in the welded area. Um, and then you can see um that's what will get rebuilt and reinstalled. If you look, there's another area that says damaged beam seats. So a little bit of the decking on the center pontoon basically picked up and came off of the beam seat.
SPEAKER_02So they're sitting about this high above the big pontoons. It just broke the bolts and it's now sitting on top of the pontoon. That has to be lifted back up, put on those beam seats. Uh, some of the beam seats need to be replaced. Um, not all of them, but some of them do. Um, it's the same thing on the other end. You can see damaged beam seats. Uh, there's a little bit of damage to one of the anodes. Um, and then some other work that's uh planned to be happening is we need to go and inspect the welds that remain. They look good, you know, from from the outside.
SPEAKER_02You look at it, you don't see anything obviously wrong with the welds, but we need to get some actual um you know instrumentation down there to to assess these welds to make sure there aren't cracks that you're not seeing or there hasn't been any failure. So that's in the works as well. Um that is in short, where we're at with the current float and installing the current float. That's that's the that's plan A, I would say.
SPEAKER_02Um see if I have anything there. This uh if you want to look at uh G910, this is the other one. Um looks like this. It's got some blue riding up in the corner. I think that the key to this one is it identifies it the head frame. We need to get a head frame in now. We always wanted a head frame, we pulled a head frame, and a headframe, I just think is highlights that go up and hold the dock up whenever you want.
SPEAKER_02We always wanted one, we pulled it, money and time, because you know, we're we're we're we knew we were time pressed for this, we knew we're money pressed for this project. In the end, you want a head frame because if you want to pull out your dock and maintenance it or whatever you may want to do to it, you can use this head frame to support your transfer span bridge that goes down there so you can float your dock out. So the intent was always to put one in, just not this time frame. Um, but with this in mind, I don't think we have a lot of choice.
SPEAKER_02So we're we're engineering that KPFF is engineering that NAT so that we can figure out um what we you know, what it's gonna cost and whether it's gonna be a static, just essentially lift it up and hold it in one place, or is it gonna be some other sort of powered hydraulic headframe? Um I think the way we're going is probably gonna be a static headframe, but uh I can't, I don't have that design yet from PPM or KPFF. I apologize. Um with all that said, I I do think it's important to note before we go on to G uh9, oh, they're both G910.
SPEAKER_02That's confusing. Sorry about that. Um that we have ran through a lot of options here. I mean, I've I've spent the last, well, since the 12th dreaming up ideas, getting them shot down primarily by engineers, uh, but also them dreaming up ideas uh to fix this. And you know, when you go look at the dock, you look at the center section, it's 270 feet long. Like, why can't we just use this intersection? But the reality of that center section is um there's no pile hoops to hold it in place, and on the back of it, there are floats that are in the way, additional floats for buoyancy due to that heavy transfer span.
SPEAKER_02So we would have to engineer hoops to go on the end, if you can imagine going on the end of it, which is totally doable to hold it in place. But that's gonna take as long as repair the you know, constructing these cross-pontoon T's. Um, and then you also are going to lose the ability to bring in those ships and breast them. So now you're gonna have to build additional dolphins in there to hold the ship because we don't have enough in there. And this dock has bollards on it, and it was you know, it was uh it was a lot of the mooring capacity of the ships.
SPEAKER_02So bringing that 270-foot section in um as is and trying to figure out how to pin it with pilots, which is I'm not saying it's not doable, it's just it's conflicting with where we're at. And steel is hard to get, we know that that's the critical path. We've ordered it, and then shop time is the next. And so if we ask, um, if if we try to do it simultaneously, at least on the West Coast, it seems like we're going to run into conflicts in the shops of making this happen. Um, so with that, we went down and we don't want to give up.
SPEAKER_02So we have a plan B right now, and it unfortunately they're both named G910, but it's the one with all the writing on it. Um, so you look at this one with all the writing on it. So this one is uh using flexi floats. So I'm gonna bounce over and I don't know how if everybody's familiar with flexi floats, but you got a picture of flexi floats. There are these steel pontoons. Um and the idea would be we'd put in some flexi floats, we'd have to get some flexi floats uh and source them.
SPEAKER_02We try to make that about 290 feet. That's the purple rectangle at the end of the transfer span. Um, when we do that, we also are going to have to take the pilings that we have on the ground. I mean, we have some extra piles that we've we've prepurchased for other aspects of this project. We have we'd probably take our template piles, which are the piles we're using to build templates to drive the current dolphins, and then they pull them out and they reuse them, and we'd put them just north of that purple rectangle. Most likely we'd have to build two dolphins there.
SPEAKER_02Um, and that that's that's a bit of work and a bit of time. We would also we have one cap, which is the cap that you put on top of these dolphins you see everywhere. We have one repurposed steel cap down there right now. Um, we'd have to come up with a second um and put it all in. With that said, then after you did that or we did that, um we would have to pull them back out at the end of the project to get the main float in.
SPEAKER_02So it's not the ideal, obviously. We're we're we're exploring it if something you know comes to a sudden halt on repairing the float, but it certainly is not the ideal. The other issue that is a problem with this project is the flexi floats probably don't have the buoyancy to hold the transfer span because it's a very heavy transfer span that goes down there, and it has elevated bearings, so we'll have to do some modification ramp no matter what we do, because the belly the bearings were meant to sit down in our current dock, and it's a it's built to accommodate that.
SPEAKER_02The flexi floats are smooth and they won't. So we'll have to come up with some modified lift to get onto that transfer span. Uh, they're still exploring that right now. Uh, I don't know. The answer to that. Um, and then as well, the you know, on the flip side, the piles seem to be going in well. We're working on the last dolphin out in the deep water, we're moving to dolphin seven on the inside, which is good. But that will mean there's no catwalks getting to these dolphins, and so we'll have to the the longshormen will have to boat out and get on the get on the the mooring system out there.
SPEAKER_02There are there will be catwalks between them all in the south, but there will be a requirement to get boated out there. Um I'm not sure how we would grab those um dolphins that we haven't designed yet, and you know, the temporary dolphins, we haven't gotten to how we would actually grab those. They're close enough to that flexi float setup that might work, but I don't have a solution to that yet. Or I, the engineers. Um and six and seven, we could probably grab from the wooden dock. But um right now, um, all of it was originally designed so you catwalked up or gangwayed up from the cruise float, the larger cruise float.
SPEAKER_02So with that in mind, we'll have some uh temporary fixes that'll have to go in place, a number of them. And I and I don't have one that gets the long shoreman out to those outside dolphins without a boat right now. Um, there's just too big a span there right now. Um see what else we have. I do want to flip, you have a final page that has uh what the temporary plan was because probably some of you like me instantly thought, well, we had a temporary plan, and this is G4.00 that we were going to use at one point.
SPEAKER_02Why can't we do that? The big problem that we have in something similar to what we were going to do with that temporary plan is we cut off the existing dock that would have caught a lot of the doors and ability to offload the ships. That's gone now. I mean, it's it's it's the ultimate plan that we want. And that would have allowed us this much smaller floating dock and that temporary uh or that concrete dock that we had before to offload the ships. Well, the the the concrete dock is gone now, right?
SPEAKER_02Just there's just a little pier sticking out now. So we don't have that longer section of concrete that we could have put doors to. Um I think that is the update in in a very convoluted way.
SPEAKER_05Manager Ryan, we appreciate that. And we appreciate all your hard work so far since this has since this began. I'm gonna open up uh uh questions to you from the uh from the assembly. Please use your judgment. I know we have uh we have executive session coming up. If you feel like the question should be answered in executive session, please note that and we'll move on. But uh questions for the manager.
SPEAKER_06Um thank you, Your Honor, and thank you so much for explaining that in a way that even I can understand. Um I just wanted to ask about our timeline. How um is our timeline best case scenario, everything goes according to plan, or is there a little bit of flexibility there?
SPEAKER_02There is flexibility. Um however, um it's it's a very I mean I I I will not try to pull the wall of your tight timeline. Um, I can say that the flexibility, one, we're trying to get to steel before the first week of March. We don't know, you're relying on the steel mills. It's hard because we're not the biggest customer right now. It's it's it's a real frustration, right? Um so that that one, there's some talk of maybe gaining a week. I hope we don't lose a week.
SPEAKER_02Um the cross-pontoon delivery, that really is dependent on the steel. Um so I don't think there's a lot in there. Um the May 2nd, where you get the repair complete, there there's some room in there, some wickle room in there. We I use 12 days um in that, I believe is what I got in there. I think it's possible to do it in six. Um, and the reason I say that is if it happens in Ketchan, they have a lot of commercial divers down there and they have a lot of support.
SPEAKER_02And so we could run two crews 24 hours a day. Um, and so that's uh some of the discussion is making that happen in in half the time, I would hope. Um, the second to the eighth is uh six days. Um we think it's four to five days to tow it up here, but with weather and the like, of course, we're worried. Um and then the installation of five days. Uh PPM does appear to be doing well out there in their pile driving. Um, and I I have to think it's not, I mean, I have to hope it doesn't truly take them five days to position the dock in place out there, assuming they're moving along at the pace they're moving along, and it's clear that we're bringing the stock in.
SPEAKER_02With all that said though, we uh we know in each of those steps there's just as many potential delays. But this is the um this is the the direction we're pushing for right now, and and we haven't it's not down to every hour, but it's it's it's a tight schedule.
SPEAKER_05Manager Ryan, when's the first day you anticipate uh using that dock? If this hadn't occurred, when's the first day you were gonna park a ship on that dock? May 14th. May 14th. That is a tight schedule. Uh Vice Mayor Potter.
SPEAKER_00Thank you, Your Honor. Can you speak to some of the um a little more of the specifics that are involved as far as actually securing the dock into place once it shows up in Skagway?
SPEAKER_02For sure. Um I'm gonna use the picture. I'll do my best, Steve. So these these four piles, the plumb piles, the straight up and down ones, one, two, three, four. They're in. And on on the back of the dock, on this section of the back of the dock, and that's the piece that came off. There are four pile hoops.
SPEAKER_02So that they go around the pile and secure it there. There's also batters that support these, you know, angled piles. So these are in, and that's what needs to hold them in place. On the 14th, what they would have done is they would have came in and gotten these secured, and they would have had temporary piles here to support it until they got these in place. As it stands, they may, I don't know if they will do this or not yet, but they may uh go ahead and drive all four of these and then bring the whole thing in and just put them all in place.
SPEAKER_02And so that's it, really comes down to getting the piles in the right spot. You know, we're supposed to have this surveyed down to the inch and straight up and down, and those four pile hoops line up. So if we get this dock all put together, it should look like this. Come in and slide into those hoops, and then you secure the hoops on it, and then you would have to lower and get the transfer span onto the dock.
SPEAKER_00And one more question, if I may. Now that we have quite a bit of the work completed, what has been about the um the average time it has taken to complete a dolphin?
SPEAKER_02I don't know that. Uh it it's none of them have gone the same. A dolphin is six piles uh or so. Um some of them have gone in relatively quick. I mean, the deep water dolphins go in pretty fast. The deepest one, the one we're most worried about, is clicking along. And I mean, it depends on whether you count the templates and then driving the piles. You know, it's a couple, three weeks if you count the templates and and and the um piles, but they haven't only been constructing a dolphin, right?
SPEAKER_02Like they switch back and forth, they move their cranes around for other things. So it's not as if they go and just drive that dolphin. They they jump around for various reasons, marine mammal delays, weather delays, and just sequencing of the project. If they were doing those inside dolphins, I think those could be expedited pretty quick, partly because they're not gonna be there for the long run, right? I think that's a different story. Um, and but but still gonna take a while. Um, so I can't give you a direct answer on that one, unfortunately.
SPEAKER_03So Lee Member Hansen. Thank you, Your Honor. Manager Ryan, can you uh summarize the engineering difference between how a dock could fail on plus a six-foot plus wave while it's being towed compared to the weather we're having right now? Um, and if I mean I I think my understanding is that because there are all the dolphins that are perpendicular that support the 500-foot float, the engineering is designed for that, but not for obviously not to haul it, um, to tow it.
SPEAKER_03It it is is I I have the question, and a lot of people have the question, if this dock is sufficient, if the engineering is sufficient, if it can't make it in an eight-foot wave, how about uh what's going on at this very second?
SPEAKER_02Yeah, so um there's a couple things. One, um there's a debate on whether it's an eight-foot wave or a 15-foot wave, right? And as I'm learning, uh, when you say a six-foot, I can't remember the term, significant wave, significant wave height, that can mean there's a factor of 1.8 to that, right? So it's nearly a it's a 10.4 foot wave. So if it's six foot, that accommodates a 10.4 foot wave. Did I get that math right? Close to that. If you go to eight foot, that that that actually goes, you know, 0.8 times 8 plus 8, right?
SPEAKER_02So that's 6.4 feet plus 8. So that's a 14.4 foot wave that you it would suffer if it was an eight-foot significant wave design. Um, but yeah, um, in addition, so this dock's going along like this, and and one of the one of the things that it was designed for, right, is this six, we'll just say a six-foot wave. Don't hold me to that. That's and that's what it's designed for to be towed. Here, the period between a wave, you know, how long it takes a wave to roll through is very tight.
SPEAKER_02So it may be a half a second. So the six-foot waves are doing this, right? There's lots of them that are touching the bottom of your pontoons and holding your dock up. When you're towing in the open ocean, you may have a period that's very long. So now you have a wave that looks like this. And when that happens, the front of the dock doesn't have as much on it. So you may have a hundred feet of this dock up in the air because you have this long period, and then it's coming down and you're towing it that way. And so that's more dramatic and more exaggerated and impactful to the dock.
SPEAKER_02So completely, I mean, not completely different, but uh but a significantly different environment being towed than sitting up here in what Skegway experience is we're wind waves, we're not swell, big difference. And wind waves here are tight, and for small boaters like me, it's terrible. For a long dock with a lot of support points, it's good. And so that's my understanding of the difference. Um, and we've had a lot of discussions about that.
SPEAKER_05Uh Burnham, do we did we get anybody on the phone uh with us yet?
SPEAKER_04Or with I believe it's possible that Assemblymember Burnham joined at uh 5.03, but I don't know if he can speak or not. Jay, can you hear us?
SPEAKER_01I can hear you. I've been listening. Um, I just had some trouble when I initially set it up. I had a hard time getting it off of mute. So, but I've been listening to the whole thing.
SPEAKER_05All right, if you if you have any questions, please let me know. Um, please.
SPEAKER_07Thank you, Your Honor. Um, manager Ryan, could you speak to the um head frame a little more? Is this something that was originally planned and then cut from the plan and now it's being put back? And um, if you could just elaborate on that a bit. Yes.
SPEAKER_02Um yeah, the head frame originally was in the project. And you and we want it in the project. Um and really, I just think of it as two posts, but you know, I I think of it very simply in my mind, but two posts with a crossbeam that holds the ramp up when you don't want it down on the dock, right? And you don't want it down on the dock for various reasons to maintain it while it's in place, to pull it out and you know, recode it someday, um, move it to the ferry peninsula someday, whatever you may want.
SPEAKER_02But that headframe, I just think of as a rectangular device that holds it up in the air. Um, you may even want to do it in in bad weather windows when you don't want it to work um on the dock and and you know, create wear on the dock. So it was in the original design and it was pulled. We you know, when I went down originally when this bid came in so high, we pulled everything we could just to get the bare bones dock in. Use the assembly put back in the deep water dolphins, which appears to have been wise. Um, and uh, we even up to a couple maybe three weeks ago, we're still considering putting the head frame back in because we already had some of the piles here.
SPEAKER_02Uh, but we chose not to for expense and truly um a lot of concern from my for myself about marine mammal take and just any delays to the project that might come from that. And so I didn't want to complicate the project any more than I had to, trying to get it done on time and not impact our marine mammal take and our um on our finances or even the the progression of the project. So um now it would, you know, in my opinion right now, it would behoove us to get it back in there because it will help expedite the installation of that transfer span.
SPEAKER_02If not, then we've got this issue with this transfer span and how we're gonna have it sitting here. And you know, the only real solution appears to be leave the Pacific lifter out there holding it or not put it in and wait until the dock shows up, which is not an option to if you want the dock in on time.
SPEAKER_05Manager Rybman, is that head frame, was that part of the original cost, or is this gonna be an additional cost if we add the head frame? It's additional. It's additional. Okay. So member Woodell.
SPEAKER_07Expanding on that question, do we already have an estimate of what that cost would be because it was something taken out before?
SPEAKER_02We don't. Um we took it out and now they're trying to get us one that's not going to be the same, right? Because we didn't order all the structural steel, so it'll be a little bit different one. So they're working up that new design, and we'll get that cost from PPM as well as as soon as we can.
SPEAKER_07Um and if that requires steel ordered as well, is that following the same projected dates that you'd written on your hand drawing over here? Like would that be the steel that arrives?
SPEAKER_02Yep. It's different steel. It's different. Yeah, that's critical path steel. The drawing is to be utilizing materials that we already have. Thank you.
SPEAKER_05Manager Ryan, when you're talking about the option B, um, how easy is it to source these flexi floats? Is that are they just laying around? We is it hard to get those?
SPEAKER_02Depends on who you believe. Um some people are telling me they're easy. Um people are telling me they don't know. Um, I don't I know that we have KPFF chasing it down to try to figure that out. We had a conversation this morning about it. They're trying to source them right now, um, but I don't have an answer. Uh PPM off-handly said they're easy to get, um, but I don't know that for sure yet.
SPEAKER_05Thank you. Vice Mayor Potter.
SPEAKER_00Your Honor, I think I just have one last question um regarding our pile supply. I think we started off with some extra ones, right? Um would these um option A or option B plans require ordering additional piles and about how many?
SPEAKER_02We believe right now that we have the piles on site. We don't know that 100%. They're doing a pile inventory. One of the issues is you if you if you looked at that option B, there's two dolphins there right now. And the issue is that hasn't been engineered to see if it will take the load of you know whether we need one or two of those, and you know, because there's going to need to be spring lines on them, and can they get them to be strong enough to hold the 100-ton ballers or the 200 tons? So I don't know the answer to that. And I know that we were looking back at the extra pilings that we have and doing a county of that, and then we also would start to uh repurpose those um template piles.
SPEAKER_02Um and that I think we'd actually have to buy those from PPM. I think they're PPM's template piles, so we might have to buy those.
SPEAKER_05Okay. Any further questions before we uh move into executive session? Okay, I'd entertain a motion to move into executive session. Vice Mayor Potter.
SPEAKER_00Thank you, Your Honor. I move we enter executive session for matters the immediate knowledge of which would clearly have an adverse effect upon the finances of the public entity, and matters which by law, municipal charter, or ordinance are required to be confidential. Discussion with a borough attorney regarding the Orr Peninsula cruise dock float, and that this executive session admit Mayor Bass, Manager Ryan, Deputy Manager Deach, Fort Director Jennings, Clerk Burnham, Deputy Clerk Carr, and additional assemblymember uh Burnham and Henry and Attorney Bob Lasco may attend via Zoom.
SPEAKER_05Second. Motion by Potter, second by Hanson, discussion Roll call Yes.
SPEAKER_04Hansen. Yes five yeses, motion passes.
SPEAKER_05Okay, we will reconvene in uh executive session in five minutes. Thank you. Okay. Um we're gonna go ahead and uh continue business here as the assembly. Um manager Ryan, thank you for and your staff for all the for the initial presentation and for your work in the executive session. Uh, can you keep please give us a uh kind of a synopsis on your plan moving forward?
SPEAKER_02Yes, um, as as lined out, um I'm moving forward working uh with PPM, TransPAC, KPFF to uh repair the dock um and deliver it to Skegway on time for the cruise ship season. Um you know in our view it's uh PPM and TransPAC's responsibility to fix it and deliver it here on time and uh get it installed intact. So we're gonna move forward with that. Um and uh work hard to be there before the cruise ship season.
SPEAKER_05All right, thank you, Manager Ryan. Any uh further discussion on uh item six here Kate?
SPEAKER_06Just wanted to show my appreciation. Thank you guys for your hard work and your thorough presentation.
SPEAKER_05Thank you. Any further discussion? All right, we'll move on to item seven, mayor and assembly discussion items. Any items for discussion tonight? Okay, any uh we'll move on to closing comments. I'll start with uh Dan. Uh somebody member Henry, any uh closing comments?
SPEAKER_04Nothing, Your Honor.
SPEAKER_05Thank you. Some member Calodi. Thank you.
SPEAKER_03Nothing, Your Honor. Thank you.
SPEAKER_01Uh Summit Member Burnham Just a regular guy who wants a pull, nothing else.
SPEAKER_05Thank you, Jay. Uh Similar Member Waddell.
SPEAKER_00Nothing at this time, thank you.
SPEAKER_05Vice Mayor Potter.
SPEAKER_00Thank you, Your Honor. Uh, want to um echo what Assembly Member Collodi said. Um staff is working tireless tirelessly. Um and and thank you for that. And I just want to reassure everyone that um there is absolutely no doubt that um it is the the importance of getting this dock um going one way or another is is not questioned by any of us up here or amongst the staff. So um thanks for your hard work, staff.
SPEAKER_05Thank you. Um and again, I this is our number one priority right now. This is what needs to be addressed. Um, this is a huge issue for our for our community. We need to get it resolved. Thank you, Brad, and your staff for uh for all the hard work so far and the continued work. That's all I have. Um and I would entertain a motion to adjourn.
SPEAKER_07I move that we adjourn.
SPEAKER_05Second. Motion by Waddell, second by Hanson. Discussion roll call Henry.
SPEAKER_04Yes, Potter Yes Hansen Yes Waddell Six Yes's motion passes. Okay, this meeting is adjourned. Thank you.
Call to Order Roll Call Approval of Minutes: November 5, 2026 Approval of Agenda Reports of Officials and Committees: Mayor’s Report Assembly Committee Reports Treasurer’s Report Manager’s Report Presentation from...
Call to Order Discussion of Rockslide Mitigation Project 65% Design: Presentation from the Design Team Questions and Answers Written Questions from the Public Questions from the Mayor and Assembly Overview of Guided...
Call to Order Roll Call Approval of Minutes: October 8, 2026 Special Meeting October 15, 2026 Approval of Agenda Reports of Officials and Committees: Mayor’s Report Assembly Committee Reports Treasurer’s Report...
Call to Order Review of Proposed FY27 Budget - CIP & Special Revenue Funds: School Funding Debt Service Permanent Trust Capital Projects Sales Tax Fund CPV Excise Tax Fund Mayor & Assembly Discussion Items Adjournment...
Call to Order Review of Proposed FY27 Budget - Operating Funds: General Fund Visitor Fund Clinic Fund Harbor Fund Port Fund Water - Sewer Fund Solid Waste Fund Mayor & Assembly Discussion Items Adjournment Packet